Question to the Ministry of Defence:
To ask the Secretary of State for Defence, pursuant to the Answer of 13 January to Question 100451 on Ajax Vehicles: Procurement, what the reasons were for the two vehicles referred to failed the inspections.
The main reasons why the two vehicles were initially rejected during General Acceptance Testing were due to vibration (vehicle 1) and a failed brake test (vehicle 2).
Both vehicles are due to be re-presented and re-tested.