Defence Equipment

(asked on 31st January 2024) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, with reference to page 37 of the National Audit Office's report entitled The Equipment Plan 2023-2033, HC 315, published on 4 December 2023, what steps he is taking to improve the red rating from the Infrastructure and Projects Authority of MODNet Evolve.


Answered by
James Cartlidge Portrait
James Cartlidge
Minister of State (Ministry of Defence)
This question was answered on 8th February 2024

Since the last Infrastructure and Projects Authority (IPA) review, the MODNET Evolve programme has appointed a new Senior Responsible Owner and Programme Director. The governance regime has been strengthened and is more robust, and the performance of the programme continues to improve. In accordance with the IPA’s recommendation, the programme has been brigaded into two technically independent capability streams, covering the Official and Secret security tiers.

The primary MODNET Official contract was signed in December and there is a clear, credible plan to migrate to the new supplier, and realise a 60% reduction in running costs.

The future Secret requirement is in the process of being revalidated to ensure the project meets Defence needs and has the flexibility to adapt to rapidly changing threats, technology, and evolving user need.

An IPA review is planned for April, where it is expected that the programme’s rating will improve.