Bypasses: Northamptonshire

(asked on 4th November 2015) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what the planned date for the (a) start and (b) finish of the A509 Isham bypass is; and if he will make a statement.


Answered by
Andrew Jones Portrait
Andrew Jones
This question was answered on 9th November 2015

The latest information provided by Northamptonshire County Council, the promoters of the A509 Wellingborough Development Link which contains the proposed Isham Bypass, is that subject to the successful completion of any remaining design and legal process, and approval by my Department, work could start on site in April 2017 and the scheme open in October 2018.