Regeneration: Essex

(asked on 2nd December 2015) - View Source

Question to the Department for Levelling Up, Housing & Communities:

To ask the Secretary of State for Communities and Local Government, pursuant to the Answer of 15 October 2015 to Question 11444, when the regeneration strategy for Jaywick will be fully implemented; and if his Department will (a) provide additional resources to improve the (i) standard of housing and (ii) quality of life and (b) liberalise planning rules for house building in Jaywick and Brooklands.


Answered by
Brandon Lewis Portrait
Brandon Lewis
This question was answered on 7th December 2015

The Jaywick Coastal Community Team are preparing their Economic Plan, to be completed by the end of January 2016. The Plan will outline the key economic issues facing Jaywick, setting out both the short term and longer term priorities for the Coastal Community Team.

The Chancellor confirmed at Autumn Statement last week that the Coastal Communities Fund will be extended from 2017-18 to 2020-21 with at least £90 million of new funding. Details of the next bidding round will be announced in the New Year. The focus of the Fund will remain on support for sustainable jobs and growth.

Tendring Council received £1.8 million in New Homes Bonus in 2015-16 and a total of £5.2 million since the scheme started in 2011-12. All new homes are constructed in accordance with Building Regulations, ensuring they meet minimum standards in respect of health, safety and sustainability.