Question to the Department for Transport:

To ask the Secretary of State for Transport, what information his Department holds on the timing of the implementation of dynamic all-lane running on smart motorways.


Answered by
Jesse Norman Portrait
Jesse Norman
This question was answered on 8th May 2019

Highways England operational staff are automatically alerted to rising traffic flows from roadside detectors. At a pre-determined threshold, operators are prompted to begin the process of opening the hard shoulder. CCTV is used to check for any stopped vehicles or obstructions in the hard shoulder. Once checked, the hard shoulder is opened to traffic by the operator implementing a speed limit sign above the hard shoulder.

The decision to close the hard shoulder is again taken based on location specific, pre-determined, traffic flow thresholds.