Crossrail Line: Railway Stations

(asked on 7th May 2019) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what proportion of the funding allocated in Control Period 5 to the Crossrail upgrade works at (a) West Ealing, (b) Ealing Broadway and (c) Acton Main Line stations has been spent.


Answered by
Andrew Jones Portrait
Andrew Jones
This question was answered on 15th May 2019

All of the funding required is in place for the remaining work at West Ealing, Ealing Broadway and Acton Main Line. The Department for Transport has regular discussions with Network Rail and Crossrail Limited regarding the Network Rail works. Network Rail closely monitors its finances through monthly reporting to Crossrail Limited.

In Control Period 5, £16.6m of funding was allocated to the build elements of the Crossrail station upgrade works at West Ealing, Ealing Broadway and Acton Main Line. Of this funding £16.6m has been spent.

In Control Period 6, £64.4m of funding has been allocated to the Crossrail station upgrade works at West Ealing, Ealing Broadway and Acton Main Line.