HMS Prince of Wales and HMS Queen Elizabeth

(asked on 5th September 2019) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, how many temporary couplings on pipework were used on (a) HMS Queen Elizabeth and (b) HMS Prince of Wales.


Answered by
Anne-Marie Trevelyan Portrait
Anne-Marie Trevelyan
Minister of State (Foreign, Commonwealth and Development Office)
This question was answered on 9th September 2019

An investigation has been conducted into the flooding incident that took place in HMS Queen Elizabeth. The incident did not involve a temporary pipe coupling and there are no such couplings in HMS Queen Elizabeth or HMS Prince of Wales.