Type 26 Frigates

(asked on 7th December 2023) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, pursuant to the answer of 14 November 2023 to Question 700 on Type 26 Frigates, what the other improvements to streamline production processes are.


Answered by
James Cartlidge Portrait
James Cartlidge
Minister of State (Ministry of Defence)
This question was answered on 15th December 2023

BAE Systems has announced that on current plans the new shipbuilding hall at Govan will be completed in 2024. The new shipbuilding hall forms a key element of the improvements the company plans to make at its Clyde shipyards. These include the digitisation of the facilities at both Govan and Scotstoun alongside a range of infrastructure and automation improvements such as tablets and kiosk screens on the shop floor to streamline production processes. The company also intends to open its Applied Shipbuilding Academy in 2024.