Baglan Energy Park: Energy Supply

(asked on 8th November 2021) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, what estimate he has made of the monthly cost of maintaining the energy supply to Baglan Energy Park after 30 November 2021.


Answered by
Greg Hands Portrait
Greg Hands
Minister of State (Department for Business and Trade)
This question was answered on 22nd November 2021

I am advised by the Official Receiver, who was appointed as liquidator as of 24 March 2021 of the Baglan Group, including Calon Energy (Baglan Bay) Ltd, Baglan Generating Ltd, Baglan Operations Ltd and Baglan Pipeline Ltd, that the estimated monthly cost of maintaining the energy supply to Baglan Energy Park after 30 November 2021 is approximately £1.2m.