High Speed 2 Railway Line

(asked on 15th July 2020) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether his Department is taking steps to (a) restructure and (b) reassess the viability of the High Speed Two project as a result of the Infrastructure and Projects Authority issuing a red Delivery Confidence Assessment rating in its Annual Report on Major Projects 2019-20.


Answered by
Andrew Stephenson Portrait
Andrew Stephenson
Minister of State (Department of Health and Social Care)
This question was answered on 24th July 2020

The IPA’s report refers to the status of the HS2 project in September 2019. This was before the project was comprehensively reset in February 2020 with a revised budget and schedule, and provision of adequate contingency. Steps have also been taken to ensure the project is delivered in a more disciplined and transparent manner with, for example, a dedicated HS2 Minister appointed and bi-annual updates to be provided to Parliament.

In line with the findings of the Oakervee Review, published in February 2020, we will also be creating new delivery arrangements for Euston, and have committed to drawing up an Integrated Rail Plan for the Midlands and the North by the end of this year.