Railways: South Wales

(asked on 6th September 2017) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what the cost to the public purse has been of electrification of the railway line (a) in the Severn Tunnel, (b) between the Severn Tunnel and Cardiff Central station, (c) between Cardiff Central Station and Bridgend, (d) between Bridgend and Port Talbot Parkway, (e) between Port Talbot Parkway and Neath and (f) between Neath and Swansea; and if he will make a statement.


Answered by
Paul Maynard Portrait
Paul Maynard
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 14th September 2017

Network Rail is delivering the Great Western Electrification Programme to the dates set out in the latest publication of their Enhancement Delivery plan.

This includes completing electrification of the Great Western Mainline to Cardiff Central by December 2018. The recent National Audit Office’s report states that electrification is expected to cost £2.8 billion.

Network Rail have advised the Department that expenditure on the mainline between Cardiff and Swansea has yet to be finalised.

Reticulating Splines