Tyne Bridge: Repairs and Maintenance

(asked on 25th January 2024) - View Source

Question to the Department for Transport:

To ask His Majesty's Government what steps they are taking to ensure that the £41.4 million funding they have promised for the restoration of the Tyne Bridge will be released in time for the works to completed for its centenary in 2028.


Answered by
Lord Davies of Gower Portrait
Lord Davies of Gower
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 7th February 2024

I am delighted that the Roads Minister announced at the Tyne Bridge last Friday, 2 February, that the Full Business Case (FBC) for the Tyne Bridge and Central Motorway A167(M) Major Road Network scheme has been approved.

The Department has agreed to provide an initial funding contribution of £35.2m towards an estimated total scheme cost of £41.4m. Following the Prime Minister’s announcement on Network North last autumn, our commitment to schemes in the Major Road Network programme has increased from 85% of cost, as estimated at the Outline Business Case stage, to up to 100%. We will announce shortly how individual schemes, including the Tyne Bridge, will benefit from this additional funding.