Question to the Department for Energy Security & Net Zero:
To ask the Secretary of State for Energy Security and Net Zero, how many renewable energy projects are awaiting a decision on their application to connect to the national grid as of 28 February 2024.
The latest data from the Electricity System Operator, from 31 January 2024, reports that there were 40 renewable energy projects awaiting transmission connection offers.