Question to the Ministry of Defence:

To ask the Secretary of State for Defence, how much his Department paid General Dynamics UK in 2023-24 for the Ajax programme.


Answered by
James Cartlidge Portrait
James Cartlidge
Minister of State (Ministry of Defence)
This question was answered on 24th April 2024

Between 1 April 2023 and 31 March 2024 the Ministry of Defence paid General Dynamics UK £437 million for the AJAX programme. All payments have been made in accordance with performance against the payment schedule and milestone plan within the extant fixed price contract. I am unable to publish the details of the milestones and payment schedule as this may prejudice the Department’s commercial interests.