Tuesday 15th November 2016

(7 years, 12 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Rosser Portrait Lord Rosser (Lab)
- Hansard - - - Excerpts

I thank the Minister for repeating the Statement made earlier today in the House of Commons. We support HS2 and thus welcome this further announcement of phase 2B on more but not yet all of the route. We welcome the intention that HS2 outside London will have connections to the existing network. We do not welcome the fact that the Government appear determined to see HS2 run in the private rather than the public sector, bearing in mind the amount of taxpayers’ money that will be invested, the success of the public sector in running the east coast main line twice following the withdrawal of two different private sector operators, and the continuing success of the public sector in running the London Underground, with its heavy traffic flows.

We will need to look at the details of the proposed route just announced and the extent to which legitimate concerns have or have not been addressed, as well as the compensation and mitigation proposals, but perhaps the Minister can say now how the compensation compares with that for those affected by a new runway at Heathrow. For how long will the further consultation mentioned in the Statement last, and by when do the Government expect to announce their decisions in the light of that consultation? The Government have not yet given a timescale on that. Likewise, when next year do the Government expect to announce the rest of the route of HS2? The National Audit Office stated earlier this year that HS2 had an “unrealistic timetable” and faced major cost pressures. What is now the timetable for the completion of HS2 and what is the latest accurate projected total cost figure, bearing in mind what has happened time-wise and cost-wise to what is presumably the much simpler Great Western electrification?

The Statement says that HS2 links up the cities of the north of England and the east and west Midlands. When do the Government intend to make firm announcements about improved rail links between the cities of the north? The Statement says in the context of a rail network for Liverpool, Manchester, Sheffield, Leeds, Hull and Newcastle that the Government will, where necessary,

“include passive provision for these services in the Phase 2b hybrid Bill, subject to agreement of funding and the supporting business case”.

In this context what exactly does passive provision mean—as opposed, presumably, to non-passive provision?

The Statement also says that:

“HS2 will free up space on our existing railways for new commuter, regional and freight services”,

and,

“will provide new options for services to towns which currently do not have a direct connection to London”.

What new commuter, regional and freight services do the Government have in mind, and what towns do the Government consider would have the option of a direct connection to London—or is that statement one simply of hope and expectation rather than fact?

The Statement refers to tomorrow’s HS2, east and west coast main lines being able to have,

“48 trains per hour to Birmingham, Manchester and Leeds”,

and that this would be up from 29 today. Perhaps the Minister could give me a breakdown of those two figures. On the face of it, they do not appear to include existing services from Marylebone to Birmingham; neither is it clear whether the existing services are only those to and from London or include those running between Birmingham, Manchester and Leeds.

The Statement also refers to phase 1, from Birmingham to London, and the award of some contracts. What percentage of those contracts, in number and value, are going to British firms? What percentage of any materials used will be imported from elsewhere and what percentage will come from within the United Kingdom? Reference has also been made to Euston station. To what extent has agreement been reached with the London Borough of Camden over the development of HS2 at Euston and its impact on the surrounding area?

Finally, I wish to raise two other points about phase 1 and need to declare an interest, as I have a home within a mile or so of the route of HS2 in the London Borough of Hillingdon. I make these two points in the context of what is stated on page 6 of the Statement:

“We have a general obligation to continue to seek further reductions to adverse impacts during the design, construction and operation of the scheme”.

Just prior to the London mayoral election the Government announced, following a meeting with the Secretary of State at which the Conservative candidate in that election was present, that they would ensure another look was taken at the case for extending the tunnelling of the route in the West Ruislip area. Can the Government tell us what the outcome of that further look is and the reason for any decision, now that the mayoral election is safely out of the way? Can the Government also say what has happened in respect of the relocation of the Hillingdon Outdoor Activities Centre, used by significant numbers of young people in particular? I have visited the site on two occasions in the company of two different Ministers—sympathetic noises were made, particularly on the second occasion. Has a suitable alternative site been found for the outdoor activities centre, since HS2 still appears to be going right across the existing site on a viaduct?

Baroness Randerson Portrait Baroness Randerson (LD)
- Hansard - -

My Lords, I started today in Marseille and travelled here by TGV, which is fast, efficient, very comfortable and has low emissions. I mention this not because I think that your Lordships will be interested in my holiday photos but because France is decades ahead of us in the provision of a network of fast, efficient rail services. On these Benches, we are firm supporters of HS2 and we welcome this announcement and the details provided today, as far as they go. We also welcome the jobs whose potential creation has been outlined but we have concerns, which I wish to raise here.

First, HS1 was opened in 2007 and it will be at least 20 years between its opening and that of the first phase of HS2. I know that the Minister has given us an indication of the timescale for the second phase of HS2 but I wish to push him on whether there is any scope for faster completion, because the great cities of the midlands and the north need this connectivity very much faster than what is outlined. While the Government make the very valid point in their Statement that HS2 will take pressure off existing lines, it is worth pointing out at this stage that those lines are already groaning under the pressure of the number of passengers and the frequency of services that have to be provided. Therefore, when one extrapolates into the future, one finds it very difficult to believe that the system will not have cracked apart by the time HS2 phase 2 is opened. My main concern is that HS2 phase 2 will drain resources, which are so badly needed, from the rest of the network. Investment is urgently required now. Last week, the Government announced that four electrification projects were being put on permanent hold. There is a shadow over some aspects of the Great Western electrification. The east coast main line is desperately in need of investment. The ORR’s statistics show how badly that line is suffering. Previous promises of investment on that line have been put on hold. I urge the Government to give us more detail about their plans for investment in existing services to reassure us that HS2 is not just a highly polished priority project being operated at the expense of the rest of the rail network. Stimulating investment in the Midlands and the north depends on very much more than HS2. It has to link into an efficient, integrated public transport service.

Finally, the mitigation measures and the detail on them are very welcome, but I ask for a more open and straightforward approach from HS2 Ltd in future. Residents and local councils report that they have often found it less than easy to deal with. I shall not repeat many of the detailed questions put to the Minister by the noble Lord, Lord Rosser, but I emphasise that I am concerned to have more detailed information, particularly on what “provision” means and on the number of services that currently run and the future expansion of those services.