Carillion Debate

Full Debate: Read Full Debate
Department: Cabinet Office
Monday 15th January 2018

(6 years, 3 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Young of Cookham Portrait Lord Young of Cookham
- Hansard - - - Excerpts

The Government have been in touch with a range of government departments which have an interest, including the Ministry of Defence. The top priority is to make sure that the catering, cleaning and maintenance services provided by Carillion continue to run effectively, and I have been assured that the contingency planning carried out by the ministry means that there will be minimal impact on service personnel and their families as a result of what has happened today.

Baroness Randerson Portrait Baroness Randerson (LD)
- Hansard - -

My Lords, the ongoing relationship with Carillion is yet another example of poor judgment at the top of the Department for Transport. Carillion is the second-largest supplier to Network Rail and, as has already been stated, the contract with HS2 was signed after early profit warnings for the company were issued. Can the Minister now assure us that the Government will review the guidelines for and operating procedures of departments across government so that concerns about financial stability are taken into account before contracts are awarded, and so that no firm can be awarded a contract unless it can demonstrate its financial viability?

Lord Young of Cookham Portrait Lord Young of Cookham
- Hansard - - - Excerpts

My Lords, I am grateful to the noble Baroness. It is worth making the point that of the seven contracts that were let post July, six were joint ventures; in other words, there was joint and several liability to undertake the work if one of them collapsed. In the case of HS2, which was the largest at £1.4 billion in total, Kier has already announced this morning that it has put in place contingency plans to ensure continuity of service. The two MoD contracts were joint ventures, as were the two HS2 ones, and so was the Network Rail contract to Carillion Powerlines. Only one relevant contract was not a joint venture where Network Rail is now transferring the work to another framework contractor.

However, the noble Baroness has made a good point. When one assesses who has won a tender, one has to do it against a number of set and published criteria. If you do not, you are up for judicial review. One of those criteria is financial stability. Clearly, whatever the test was back in July, it was passed. It relates to a point made by my noble friend Lord Lawson, which is whether one should take this opportunity just to stand back and look at whether the criteria used for assessing financial stability are correct and robust enough or whether they need firming up.