Rail Timetabling

Huw Merriman Excerpts
Monday 4th June 2018

(5 years, 11 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
John Bercow Portrait Mr Speaker
- Hansard - - - Excerpts

What a delicious choice: my former constituency chairman, the hon. Member for Horsham (Jeremy Quin), and an Arsenal fan behind him, most of whose family live in my constituency. I do not want to be unkind to Horsham, but it has got to be Huw Merriman.

Huw Merriman Portrait Huw Merriman
- Hansard - -

Thank you, Mr Speaker—I’m always your man.

In the two years that the Secretary of State for Transport has been in post and I have sat on the Transport Committee, he has always been very honest, open and direct about the need for change. For any project management exercise to fail to get the sign-off from Network Rail and for it to find out only three weeks before, by which time it is too late to turn the oil tanker around, has got to be a spectacular failure. Who was the project manager and penholder for this exercise?

Chris Grayling Portrait Chris Grayling
- Hansard - - - Excerpts

That is a very interesting question. My view is that the Network Rail timetabling process has gone badly wrong, and I cannot understand why GTR did not raise the alarm. I have asked Professor Glaister to go through all this because I want to understand exactly where the accountability should lie and be able to take appropriate action.