Railways: Electrification Debate

Full Debate: Read Full Debate
Department: Department for Transport

Railways: Electrification

Lord Snape Excerpts
Tuesday 19th January 2021

(3 years, 3 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

As I have noted, the Government will publish in spring 2021 the transport decarbonisation plan, which will take a holistic and cross-modal approach to achieving net zero. However, this Government have electrified 700 miles of track in the last few years; we have a very ambitious electrification programme, which goes through the rail network enhancements pipeline to make sure that the right schemes are prioritised and that it secures value for money.

Lord Snape Portrait Lord Snape (Lab)
- Hansard - -

Will the Minister accept that these things, to use her words, take a long time because successive Governments, including this one, keep putting them off? Would it not make more sense to have a proper rolling programme of electrification that would meet the aspirations of the noble Lord, Lord Bradshaw, and help bring about stability in the industry for those responsible for electrification? Finally, would it not also help the Government’s carbon reduction targets?

Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

My Lords, these things take a long time not because of delays but because of all the quite correct processes that these schemes need to go through. The noble Lord points out that the Government need a long-term electrification plan. That is exactly what the rail network enhancements pipeline is: it looks at all the potential schemes, prioritises those that produce the best overall benefits and secures value for money for the taxpayer.