New Covent Garden Market Debate

Full Debate: Read Full Debate
Department: HM Treasury
Tuesday 2nd July 2019

(4 years, 10 months ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Chris Heaton-Harris Portrait Chris Heaton-Harris
- Hansard - - - Excerpts

I agree. I thank the hon. Lady for her contribution and the way she represents the market in this place. I regularly speak to various of my old friends—I think they are friends; lots of them were customers or people I bought things from, so perhaps they are business associates—and I know that she is a very good representative of the market who talks to the tenants a great deal and represents their concerns wisely.

We are squeezing a big, successful business into a smaller space. The market had a massive footprint, and when I was trading there a lot of it was not used effectively, so it is possible to understand some sort of consolidation, but the scale we are talking about now makes that an interesting prospect. At a time when the turnover of the businesses in the market is growing, it seems odd to reduce the market’s footprint. Although the tenants are not over-happy with the overall reduction in size, they have tried their best to make it work. Various pieces of land have already been sold off, and in some instances they are sold on again. The market area is to be reduced even more. Among other changes, the temporary flower market site will be incorporated into the main site. In essence, we are squeezing a quart into a pint pot and hoping that the businesses inside the pot do not get squeezed.

Over the years, the tenants have repeatedly raised concerns through their association that the proposed end-state configuration of the market that the authority is now engaged in building will not be able to operate successfully because the proposed layout and footprint simply will not accommodate the vehicle movements needed for the market to operate effectively and efficiently. The tenants of the market are very knowledgeable—and, indeed, vocal—about how the business of the market works, and their opinions about whether what is proposed will work should carry significant weight. They have retained the services of a specialist transport consultant, who advises that there are significant failings in the transport analysis and planning undertaken by the market authority. The Minister is well aware that the market authority is a public body that has a statutory duty to provide functioning market facilities and prevent traffic congestion on the market land.

The market authority is currently redeveloping the market under a contract entered into with the developer, Vinci and St Modwen Properties, in 2015. The developer commenced the main works in October 2018. Since then, an independent logistics consultant, instructed by the tenants association, has confirmed that, as designed, the market will not be operationally viable in parking and loading/unloading terms, and will therefore constrain the businesses it contains. The market authority has allowed the developer to start the construction works, but there are problems, because the tenants say that that has happened without the authority having taken the tenants’ logistics consultant’s advice about the design, and without its waiting to see the final report prepared by Arup, a logistics consultant instructed by the developer, which confirmed that the new market, as presently designed, would not be operationally viable. Arup’s final report said that to make it viable certain measures identified in a list contained in that report would need to be adopted. I am told that Arup had been asked by the market authority to use transport data that was known to be out of date and inaccurate when assessing the viability of the options, but it still came to that quite drastic conclusion.

The market authority has power under its contract with the developer to require changes to be made to the design of the market, but it has yet to decide to follow up Arup’s advice. Instead, the developer presses on with the works as they stand. I wonder whether my hon. Friend the Minister is comfortable with that decision. I also wonder whether the Department for Environment, Food and Rural Affairs has been provided with a report from a logistics consultant—or any report—confirming that, contrary to the view of either the tenants association’s logistics consultant or Arup itself, the current design will be operationally viable. If so, would it be possible for the tenants to see it, to give them some comfort that these changes will work?

This is where my old life as a tenant of the market comes into its own, because battles over rent were legendary back in the day when I worked in the market: in April this year, the market authority sent notices to terminate the tenancies of market tenants and threatened, in a letter from its solicitors, that if tenants did not immediately agree to give up their statutory right to apply for a new tenancy and agree to vacate their units at the expiry of the notice, they would not be offered tenancy of a unit in the newly developed market and would have to depart the market instead.

Teresa Pearce Portrait Teresa Pearce (Erith and Thamesmead) (Lab)
- Hansard - -

It is my understanding that one of the key roles of the Covent Garden Market Authority is to nurture good relations with tenants. How do such actions nurture good relations?

Chris Heaton-Harris Portrait Chris Heaton-Harris
- Hansard - - - Excerpts

I know that changes at the top of the market authority have been welcomed by the tenants, and that much better conversations are being had now than have been had for many a year, but I do not believe that this is an appropriate way for a public authority to behave.

Additionally, the new draft leases issued by the Covent Garden Market Authority are removing the rights of the wholesale tenants to operate in the critical and traditional way on the bit of the market that everybody loves so much, the buyers walk or trading floor, turning that essential space into a corridor rather than a market. I can honestly tell the Minister that removing that space will almost completely remove the heart, soul and character of the market.

In the new leases, the market authority has also changed the rent negotiation process and general service charge calculations, as it has now declared that it is in fact a commercial landlord. Those actions will inevitably result in many of the smaller companies based at the market closing as the site becomes unaffordable.

Since the whole process started, there have been vast changes in how the market operates. Goods are now mostly chilled instead of being stored at ambient temperatures, and businesses’ being able to unload big lorries, repick orders and deliver in quick time continues to reduce the number of large vehicle movements required on London’s roads. However, that makes the traffic studies more important than most people believe. There is yet to be a traffic study conducted that says the future design of this important food distribution hub for London will work; indeed, all those that have been done, or at least those that are in the public domain, say that it will not. If it does not work, the market will eventually die. All the catering outlets, restaurants and food businesses currently served by the market will not go away; they will simply be catered for by businesses that travel many more miles to get into London, further adding traffic and pollution in this great city of ours.

I do not think we can ignore the facts, stand back and allow the developer and the market authority to build a market that is functionally inoperable. Action must be taken. I hope that the Government have given due consideration to the effect on tenants, businesses and the wider economy if the market were to go into decline or fail altogether. There is no need for that to happen.

I would like to think that the Minister, whose knowledge of and commitment to solving these issues is both impressive and welcome, will continue to ask those on all sides of this debate to come together to find a mutually agreeable and workable solution—all sides meaning the market authority, the tenants, the developer and the Department itself. This needs to be sorted before millions of pounds are wasted in court and one of the most vibrant parts of London’s market culture possibly ceases to be.