Question to the Ministry of Housing, Communities and Local Government:
To ask the Secretary of State for Housing, Communities and Local Government, what data his Department holds on the average time taken to complete cladding remediation works on residential buildings of approximately 20 to 25 storeys; what evidence underpins an estimated 24-month completion timeframe for such projects; and whether he will publish a percentage breakdown of remediation projects completed within 18 months, within 24 months, and beyond 24 months.
The Department’s data collection is focussed on height thresholds as this is the current determinant of programme eligibility. We expect buildings of 20 to 25 storeys to make up a very small proportion of those requiring remediation.
Based on the reported remediation start and completion dates, and storey information provided for the 24 buildings known to be 20 to 25 storeys, which have completed remediation and for which start and end dates have been reported, the average time taken to complete remediation on site is 24 months.
The Department does not work to an assumption on the time take to complete remediation of buildings of this height group (20 to 25 storeys) - and does not currently publish information on the time taken to complete remediation.