Manchester-Sheffield Railway Line

(asked on 12th December 2017) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what steps his Department is taking to eliminate the single line bottleneck through Dore & Totley station on the Hope Valley railway route between Sheffield and Manchester.


Answered by
Paul Maynard Portrait
Paul Maynard
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 20th December 2017

As part of the Great North Rail Project, the Hope Valley and Dore capacity schemes will increase track capacity to allow a more frequent service, accommodating three fast trains an hour between Sheffield and Manchester. This scheme is currently subject to a Transport and Works Act Order application, to which the Department is currently considering.

Reticulating Splines