High Speed 2 Line: Staffordshire

(asked on 5th March 2024) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, if he will publish the value engineering report for the design of the proposed Handsacre Junction of HS2.


Answered by
Huw Merriman Portrait
Huw Merriman
Minister of State (Department for Transport)
This question was answered on 11th March 2024

There have been no value engineering reports on Handsacre junction since Network North. Previous decisions to change the design of Handsacre junction were made to reduce costs and disruption for passengers on the West Coast Main Line during construction, which was value for money given the previous plan to deliver Phase 2a on an accelerated timeframe would have resulted in the use of the junction for more than 1 train per hour in each direction only for a very short period.