National Grid: Batteries and Renewable Energy

(asked on 29th March 2023) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what steps he is taking to facilitate grid connections to allow the deployment of (a) renewables and (b) battery storage projects.


Answered by
Graham Stuart Portrait
Graham Stuart
This question was answered on 17th April 2023

The Government works with Ofgem and network companies to accelerate connections by releasing network capacity and improving the connections process. As part of this work, the Electricity System Operator is seeking expressions of interest, by 30 April 2023, from developers who are willing and able to connect earlier than their allocated connection date. The Government will publish a Connections Action Plan in the summer, which will articulate actions by government, Ofgem and network companies to accelerate network connections, including for renewable energy and battery storage projects.