To ask the Secretary of State for Energy Security and Net Zero, to which (a) businesses and (b) locations his Department provided funding through the Offshore wind manufacturing investment support scheme.


Answered by
Graham Stuart Portrait
Graham Stuart
This question was answered on 27th June 2023

Through the Offshore Wind Manufacturing Investment Scheme fund, SeAH Wind received £17 million to build an XXL monopile foundation manufacturing facility in Teesside; JDR Cable Systems received £14 million to build a subsea cable factory in Northumberland; Smulders received £7 million to enable the manufacture of transition pieces at their facility in Wallsend and South Tees Development Corporation received £20 million for work at the Teesworks Offshore Manufacturing Centre.