To ask the Secretary of State for Transport, what his Department's timescales are for (a) the completion of repairs to the Ouse bridge on the M62 near Goole, (b) the removal of the temporary speed limit and (c) the full reopening of all lanes to traffic in both directions in that area.


Answered by
Guy Opperman Portrait
Guy Opperman
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 2nd May 2024

National Highways are due to complete repairs on the Ouse bridge by September 2024 when the temporary speed limit will be lifted, and all lanes opened to traffic in both directions. Whilst there will be some residual work after all the lanes open, it will not impact road users.