Infrastructure

(asked on 9th October 2026) - View Source

Question to the HM Treasury:

To ask the Chancellor of the Exchequer, how many projects have left the portfolio in each year since NISTA began reporting because they were a) completed and b) cancelled; what the i) value and ii) cost of cancellation was of those projects; and what the lead department was for those projects.


Answered by
Emma Reynolds Portrait
Emma Reynolds
Chief Secretary to the Treasury
This question was answered on 19th October 2026

In the 2025-26 financial year, 26 projects left the Government Major Projects Portfolio (GMPP) having successfully delivered their intended objectives, while seven projects left the portfolio following a decision to stop the project or bring it to an early closure. For further information on these projects, including project costs and lead departments, I refer the Hon. Member to the annual reports published to date by the National Infrastructure and Service Transformation Authority (NISTA):