Question to the Department for Transport:
To ask the Secretary of State for Transport, how many trains between Waterloo and Christchurch have been (a) cancelled and (b) delayed for more than 15 minutes since South Western Railway was brought into public ownership.
South Western Railway (SWR) were brought into public ownership on 25 May 2025. Since this date, 9.5 per cent of trains have been cancelled and 12.9 per cent of trains have been delayed by more than 15 minutes between London Waterloo and Christchurch. These cancellations and delays were not a result of the move to public ownership and could have equally occurred under private ownership. The new Managing Director for SWR, Lawrence Bowman, has been tasked with developing a detailed plan to improve SWR performance.