Question to the Department for Science, Innovation & Technology:
To ask the Secretary of State for Science, Innovation and Technology, with reference to the press release entitled US-UK pact will boost advances in drug discovery, create tens of thousands of jobs and transform lives, published on 16 September 2025, whether her Department has undertaken an impact assessment for the projected (a) water and (b) energy usage for the data centres announced.
Developers are responsible for undertaking environmental impact assessments for new data centres, including assessments of water and energy usage. As part of the criteria for hosting an AI Growth Zone (AIGZ), applicants must demonstrate access to sufficient water resources to support at least 500MW of AI infrastructure. This includes written confirmation from the relevant water supplier detailing volumes available, infrastructure requirements, and wastewater discharge plans.
DSIT are working closely with DESNZ to ensure AI energy demand aligns with future energy planning and ensure long-term sustainability.