A12: Repairs and Maintenance

(asked on 10th December 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, if she will make an assessment of the changes in costs for the A12 widening scheme following the decision taken by the Secretary of State to pause that scheme in July 2024.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 6th January 2026

The A12 scheme was deferred by the previous Government, adding to the overall cost of the scheme as set out in the table below.

Date

Estimated outturn cost

Source

December 2014

Expected cost category £100m–£250m

Published list of RIS1 schemes and cost bands https://www.ciht.org.uk/media/4382/roads-investment-strategy-summary-of-schemes.pdf

March 2016

Funding envelope of £750 million

Published Options Appraisal Report: A12 Chelmsford to A120 Options Assessment Report OAR.pdf

September 2022

£1,045-1,268 million

Published Funding Statement for Development Consent Order: Microsoft Word - TR010020_APP_1.1 - Introduction to the Application

In July 2025, following the conclusion of the Spending Review, the Government took the difficult decision not to proceed with the A12 scheme, to provide certainty for the public.