National Grid

(asked on 7th September 2023) - View Source

Question to the Department for Energy Security & Net Zero:

To ask His Majesty's Government what additional capacity they forecast is needed on the National Grid to accommodate the level of demand from the anticipated increase in the number of electric vehicles by 2030; and what additional capital costs are required by such increase in capacity for transmission and distribution per annum up to 2030.


Answered by
Lord Callanan Portrait
Lord Callanan
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 19th September 2023

The Electricity Networks Strategic Framework sets out the Government’s approach to readying the network for the increase in peak electricity demand anticipated as we electrify transport and other sectors. We expect peak electricity demand to increase to approximately 80 GW in 2030 of which electric vehicle demand makes up approximately 10%, before any demand side response. Due to existing spare distribution network capacity, we do not expect this to lead to any significant rise in distribution network capital costs before 2030. We expect £30 billion of transmission network investment between 2023 and 2030.

Reticulating Splines