Question to the Department for Energy Security & Net Zero:
To ask His Majesty's Government which components of the supply chain for nuclear power stations will be manufactured in the UK, and which components will be brought in from abroad.
The use of components manufactured in the UK will differ on a project-by-project basis. However, the building of nuclear power stations creates significant opportunities for UK companies, with EDF estimating that the current Hinkley Point C project spends 64% of construction value with British businesses. Sizewell C Ltd plan to award 70% of construction value to UK businesses, while separately Great British Energy – Nuclear’s ambition is to deliver 70% UK content across the small modular reactor fleet.