Railways: North of England

(asked on 22nd February 2024) - View Source

Question to the Department for Transport:

To ask His Majesty's Government, further to the Written Answer by Lord Davies of Gower on 12 February (HL1979), when the train service specification for the TransPennine route was last revised and passed to Network Rail.


Answered by
Lord Davies of Gower Portrait
Lord Davies of Gower
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 6th March 2024

A number of train service specifications were developed as part of the Business Case development process for TransPennine Route Upgrade. This was last provided to Network Rail in 2023 as part of a review of the integration between other major infrastructure programmes. The final train service specification has yet to be finalised and approved.