High Speed 2 Railway Line: Wendover

(asked on 26th October 2016) - View Source

Question to the Department for Transport:

To ask Her Majesty’s Government whether HS2 Ltd used current HM Treasury tunnel project modelling when they costed proposals for the Wendover short mined tunnel.


Answered by
 Portrait
Lord Ahmad of Wimbledon
Minister of State (Foreign, Commonwealth and Development Office)
This question was answered on 8th November 2016

The cost estimate for the short mined tunnel proposals at Wendover were based on the specific topography at that location, the individual tunnel requirements and the appropriate construction rates.