Railways: North of England

(asked on 11th March 2024) - View Source

Question to the Department for Transport:

To ask His Majesty's Government, further to the Written Answer by Lord Davies of Gower on 6 March (HL2700), when they expect the train service specification for the TransPennine route to be finalised and approved.


Answered by
Lord Davies of Gower Portrait
Lord Davies of Gower
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 25th March 2024

Network Rail will be using standard industry processes to progressively formalise train service changes as the programme progresses, in line with the TransPennine Route Upgrade’s (TRU’s) key delivery milestones. The last stage of the fully approved timetables will be in place in the early 2030s when the full service uplift, which TRU enables, is able to come on line.