North Wales Coast Line: Electrification

(asked on 16th June 2025) - View Source

Question to the Department for Transport:

To ask His Majesty's Government whether they have any plans to commence the electrification of the Crewe to Holyhead railway line.


Answered by
Lord Hendy of Richmond Hill Portrait
Lord Hendy of Richmond Hill
Minister of State (Department for Transport)
This question was answered on 24th June 2025

The previous government committed to electrification of this line, however no funding was ever made available to begin exploring the costs and benefits of such an enhancement.

This government has recognised the lack of investment in Welsh railways and made a real commitment, via the recent Spending Review, of at least £445 million over the next ten years for the country’s long-term rail infrastructure needs. We will work with the Welsh Government to agree how this is applied to routes across Wales and the Borders.

Reticulating Splines