East Coast Main Line Investment

Debate between Lord Johnson of Marylebone and Rachael Maskell
Wednesday 17th October 2018

(5 years, 6 months ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Lord Johnson of Marylebone Portrait The Minister of State, Department for Transport (Joseph Johnson)
- Hansard - -

It is a pleasure to serve under your chairmanship, Mr Owen. I congratulate the hon. Member for Newcastle upon Tyne North (Catherine McKinnell) on securing the debate and on giving us the opportunity to discuss investment on the east coast main line. She is the chair of the APPG which, as she mentioned, I was pleased to attend a meeting of earlier in the year. She takes great pride in the railway and its contribution to her region of the north-east. The Government very much want to build on that heritage and ensure that we leave a railway that is stronger for future generations.

As the hon. Lady says, the east coast main line is a great national asset. Its sheer scope makes its huge importance to the national economy absolutely inevitable. It runs from London, through the east midlands, Yorkshire and Humberside, north-east England and reaches Scotland. The scope of the line speaks for itself. The extent of that scope creates wonderful opportunities for communities that depend on the line to access many other parts of the country, such as the region so well represented by my hon. Friend the Member for Cleethorpes (Martin Vickers).

That said, the route is not without areas that need investment. The Government are committed to ensuring that we provide the money, time and resources that those areas require. I will take a few moments to describe to right hon. and hon. Members some of the investments that we are making in the east coast main line. However, before doing that, I will quickly respond to some of the more general points made about the distribution of transport infrastructure spending across the country, which is obviously a subject of great importance to Members for understandable reasons.

The chair of the Transport Committee, the hon. Member for Nottingham South (Lilian Greenwood), criticised the Government’s appraisal methods when deciding where to spend transport infrastructure funds. We do not accept that our methods do not provide regions with a fair share. As her Committee acknowledged, it is difficult to assign benefits specifically to one region from spending in that region when we have a national system such as the rail system. Benefits often spread beyond the area in which a specific investment is geographically located.

However, the Government have long acknowledged that the economy is imbalanced and needs rebalancing, and that changing the distribution of transport infrastructure spending to redress past patterns of underinvestment is an important part of what we need to do as an economy. We will therefore invest significantly in the north of England over the next few years. For example, between now and 2021, we will invest £13 billion in transport infrastructure in the north of England. Some of our biggest transport infrastructure items will be in the north of England, such as the trans-Pennine upgrade, which has been allocated £2.9 billion for the next five-year spending period from 2019 to 2024.

It is often asserted, seemingly without challenge, that the south gets more planned transport infrastructure spending from central Government than the north, but analysis by the Infrastructure and Projects Authority suggests otherwise: for the next four years, it reckons that the three northern regions will receive more per head than southern regions.

Let me focus on what the Government have been doing to ensure that the east coast main line continues to play an important role in our national economy. Hon. Members will be aware of the £5.7 billion Government-led intercity express programme—the new trains to which hon. Members have referred. The programme will provide the east coast and Great Western routes with a completely new fleet of trains equipped with the latest technology. The trains are being built at Hitachi’s County Durham factory, which is home to more than 700 permanent staff and supports thousands more in the national supply chain. Up to 70% of the train parts will be incorporated from sources in the UK. The full roll-out should be complete by 2020, as planned. As part of the programme, Hitachi has invested in a new state-of-the-art maintenance facility at Doncaster and has enhanced other ageing depots along the length of the line.

As I informed the hon. Member for Newcastle upon Tyne North in my letter last month, and as she mentioned in her speech, the Prime Minister has announced funding of up to £780 million in control period 6—the next five-year planning period—for the east coast enhancements programme. The programme will provide funding for important works, some of which the hon. Lady mentioned; they include power supply upgrades between Doncaster and Edinburgh, a new rail junction at Peterborough, modifications at Stevenage station to allow turn-back, and track remodelling at King’s Cross station. Together, those works will reduce congestion and enable more services to operate.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

Will the Minister explain why there has been a reduction in the amount made available to provide the upgrade when £900 million was requested?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

First of all, I would point out that this money represents a very significant increase in spending on the east coast main line. In control period 5, from 2014 to 2019, we spent about £400 million on upgrades to the line. In control period 6, that amount will increase to £780 million—it will almost double. To cast that increase as a reduction does an injustice to the Government’s ambition for this section of our network. That spending will be coupled with a £5.7 billion programme of investment in the new rolling stock, a significant proportion of which will result in increased capacity and more comfortable journeys for passengers along the east coast main line—that cannot be described as a reduction.

Of course, there will always be bids for further Government spending on all bits of the transport network. They cannot all be accommodated at the same time, but as and when business cases develop for specific pieces of work, they can be considered as part of our enhancement programme.

--- Later in debate ---
Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

May I deal with a specific point raised by the hon. Member for Jarrow (Mr Hepburn) about the trains and the line? He questioned whether they would operate at their potential. The top line speed on the east coast main line is 125 mph, and the new Hitachi Azuma trains will run at that speed. Passengers will benefit from journey time improvements delivered as a result of the trains’ improved acceleration and reduced dwell times in comparison with the existing fleet. Some of the passenger benefits from saved journey times are striking: journeys will be 10 minutes quicker between London and Newcastle, 15 minutes quicker between London and Edinburgh, and so on up and down the line. Those time savings should be celebrated.

The hon. Member for York Central (Rachael Maskell) mentioned issues with electromagnetic interference on IEP trains. Hitachi and Network Rail are working together to resolve those electromagnetic compatibility issues and ensure that new trains can operate in electric mode when they enter service as soon as possible.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

I was referring to the cabling of the trains and to the fact that passengers or members of the public could climb up on the roof. There was an electrocution on a Pendolino train because of that design, yet those trains are still running on the Great Western route, even though the Office of Rail and Road has stopped them running on the east coast.

Albert Owen Portrait Albert Owen (in the Chair)
- Hansard - - - Excerpts

Order. I remind the Minister of the time constraints, especially if he wishes to allow the mover of the debate to wind up.

Oral Answers to Questions

Debate between Lord Johnson of Marylebone and Rachael Maskell
Thursday 11th October 2018

(5 years, 6 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

The son of the hon. Gentleman’s constituent clearly had a terrible experience, and our sympathies go out to him. The Department is working closely with train operating companies on the Secure Stations Scheme, to give more stations across the network accredited status. CCTV will have an important role to play in stations, just as it does in the new rolling stock that we are introducing across the country. I remind Opposition Members that we want more staff working on our railways, not fewer, and for operators where there have been disputes relating to staffing levels, such as Southern and South Western Railway, that is indeed the case.

Rachael Maskell Portrait Rachael Maskell (York Central) (Lab/Co-op)
- Hansard - - - Excerpts

Every day, women make choices on the basis of their safety, continually planning, checking and trying to read situations. Since 2012, sexual crime has seen a staggering 167% increase on our railways, to a record 2,472 cases last year. Women are 13 times more affected than men and the highest increases are in areas where trains operate without guards. What strategy are the Government deploying to ensure that all women feel, and are, safe?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

All passengers and all women must feel safe when travelling on our trains. The Department takes this issue exceptionally seriously, as do all train operators and the British Transport police. In concrete terms, Project Guardian is ensuring that the reporting of sexual offences becomes easier than ever before. We have introduced a new discreet safe texting service, 61016, which has encouraged much greater reporting of sexual harassment on trains or assaults of a sexual nature—[Interruption.] Guards and conductors have not been removed from trains, as Opposition Members are suggesting. It is very frustrating that that line is being propagated in this misleading way. Driver-controlled operation means tasks such as closing doors can now be performed safely by the train driver, freeing up more time for guards to look after passengers, including women.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

Public order offences also rose by 116% over the same time period. A staggering 11,711 violent crime offences were committed just last year, with a total of 61,159 criminal offences in 2017-18, again hitting record highs. As we know, the presence of people in authority reduces the prevalence of crime, so can the Minister tell the House why he supports removing guards from trains—the very people who are passenger safety champions?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

We want the railways to be safe. In terms of crimes per million passenger journeys, they are safer than they were a decade ago. There are 19 crimes per million passenger journeys today, and a decade ago there were 30 crimes per million passenger journeys, but that is still too many and we want crime levels to come down. That is why the British Transport police are focusing on this very carefully. We have better reporting schemes, such as 61016, which I mentioned. As I said, we want more staff working on our railways, not fewer. That is the case for operators such as Southern and SWR, where there have recently been disputes.

Oral Answers to Questions

Debate between Lord Johnson of Marylebone and Rachael Maskell
Thursday 5th July 2018

(5 years, 9 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

Rail operating companies will be held responsible for that portion of performance for which they are responsible and accountable, and that is now under way. The Secretary of State has set in train a hard review of GTR, and at the end of that hard review, all appropriate options will be on the table and available to the Secretary of State and to the whole Government.

Rachael Maskell Portrait Rachael Maskell (York Central) (Lab/Co-op)
- Hansard - - - Excerpts

It was a Labour Government who established the NHS, and today we thank all who have served in it since.

Following the Secretary of State’s statement on the timetable chaos to the House on 4 June, he said in his response to the hon. Member for Cleethorpes (Martin Vickers) that, with regard to compensation, the train operating companies

“will have to meet the cost of that.”—[Official Report, 4 June 2018; Vol. 642, c. 59.]

That is so untrue. It is Network Rail that will be funding the compensation. Last year alone, it paid out £482 million through schedules 4 and 8. Does the Minister agree that, while the operating companies write the cheques, it is the state that pays?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

The Secretary of State has always been clear that we will review where responsibility lies, and the rail industry will be responsible for undertaking that appropriate compensation to make sure that passengers have the right redress. As Members will be aware, the rail industry is partly in public control through Network Rail and partly run by private operators. Each will pay its fair share.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

Astonishing. Network Rail paying compensation means that this is coming from the public, so, in effect, passengers will be funding their own compensation for delayed and cancelled trains, for missing exams, for being sacked from their jobs or for lost business revenue—passengers paying their own compensation. How much has the Minister budgeted for to pay compensation for the Secretary of State’s decision to press ahead with this rail timetable chaos, or will he instead cut more Network Rail projects to pay for it?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

As I have already said, the compensation involves four weeks’ cash compensation for passengers on the most severely disrupted routes on Northern services and one week’s compensation further afield in Yorkshire. Similarly, GTR announced yesterday a comparable package of special compensation for passengers on the most affected Thameslink and Great Northern routes.

Northern Rail Services: Greater Manchester

Debate between Lord Johnson of Marylebone and Rachael Maskell
Wednesday 6th June 2018

(5 years, 10 months ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

That is a good question, and one of the things that Stephen Glaister’s review will be looking at very carefully. It will look at all the processes that went into the creation of the May timetable and all the planning and preparation around it, to answer those kinds of questions and to see what lessons can be learned for future timetable changes, including the December timetable change. I will come on to compensation, if the hon. Lady hangs on for a second; I want to ensure that I complete the account of how we got to the May timetable change and what lessons we can learn from that.

I was talking about the training of drivers. Some drivers have been unavailable for their normal train-driving duties while they were and are undergoing that training. To make a difficult situation worse, Northern was unable to ask its drivers to work on their rest days for the last three months of this period, because, as hon. Members will know, ASLEF declined to extend the rest day working agreement that ended in February. That meant that Northern has not been able to absorb those exceptional or last-minute training needs and provide the additional flexibility for the train driver rosters that it needed to.

Let me turn to the questions about who knew what, when, and about where the DFT was in all this. In January, Network Rail informed the Department that it would not complete its upgrade of the Manchester to Preston route in time for the May timetable change. In response, Northern developed a new timetable in a compressed period and briefed stakeholders on the reasons why that was required. Following that, the late completion of the Blackpool to Preston blockade in mid-April meant that Northern had less time to complete those plans and its driver training. Northern then did not finalise its plan for the timetable until three days prior to its introduction. Industry readiness boards assured the Department and the Secretary of State that the timetable was ready for introduction, and the Department was not made aware of any expectations of high levels of cancellations.

Hon. Members have asked about compensation to reflect the significant inconvenience experienced by passengers. There is no doubt, and the Department accepts, that Northern passengers have faced totally unsatisfactory levels of service. I have met with many colleagues in the House, and I have also heard directly many stories from the travelling public of how the disruptions have impacted the lives of all those constituents.

It is entirely right for all those affected by the disruption to be properly compensated. I encourage passengers, in the first instance, to continue to use Northern’s Delay Repay compensation mechanism for affected journeys. Northern operates the Delay Repay compensation system for all its passengers. Under that scheme, as hon. Members will know, passengers are entitled to claim compensation for each delay of 30 minutes or more that they experience, whatever the cause of the delay. There are no exclusions for weather or other delays outside the control of the rail industry.

The Office of Rail and Road guidelines require train operators to respond to claims within 20 days of their receipt. Northern has assured the Department that it is working hard to respond to all claims within industry standards. I acknowledge the complaints that the hon. Member for Bolton North East has made about various aspects of the Delay Repay scheme. The Department is discussing with Northern ways in which we expect it to reduce its processing time for Delay Repay claims.

In his statement on Monday, the Secretary of State announced that, in addition to the standard Delay Repay compensation mechanisms, there would be a special compensation scheme for Northern passengers, subject to agreement by the board of Transport for the North. It is to be funded by the rail industry and will ensure that regular rail customers receive appropriate redress for the disruption that they have experienced. The industry will imminently set out more detail of the eligibility requirements and how season ticket holders can claim. However, the Secretary of State has already indicated, at a high level, that he expects that the scheme should offer Northern passengers who have experienced protracted disruption of this kind similar entitlements to those under Southern’s passenger compensation scheme last year.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

Can the Minister set out exactly who he means by “the rail industry”? Clearly, we are talking about Network Rail, which is culpable for some of the issues, as well as the Department for Transport and the operators themselves.

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

I want to allow us a few days to refine the details of how the compensation scheme will work. We are working carefully with all players in the industry to ensure that a fair scheme is put forward that adequately provides redress to passengers. The Secretary of State has been clear that this will be funded by the industry. We will be bringing forward further details imminently, which I hope will answer the hon. Lady’s question.

What are we doing concretely to fix the problems that have occurred? Acting through the Rail North Partnership, the Department for Transport has put in place an action plan with Northern, which includes improving driver rostering to get more trains running now, increasing driver training on new routes, additional contingency drivers and management presence at key locations in Manchester, and putting extra peak services in the timetable along the Bolton corridor. Northern has also announced that, until the end of July, it will run fewer services than were originally planned, per the May timetable, to give passengers greater certainty and to increase opportunities for driver training. I believe that this temporary measure is necessary to stabilise the service, enabling improvements to be introduced gradually. Northern will then get back to a full timetable service.

The interim timetable, rolled out on Monday, will see an approximately 6% reduction in the number of train services—about 165 out of the normal 2,800 daily services. Northern is expecting to start to see significant improvements this week, from today, as their drivers are fully rostered on to the new interim timetable. The timings for today, as of 10.35 am or so, saw Northern achieve 86% on the public performance measure. With 665 or so trains operated, 2% were very late or cancelled, which is about 15 trains. There is positive progress here. This is Northern’s best weekday morning performance since the timetable changed. That 86% compares with weekday out-turns of between 60% and 70% for the first two weeks following the introduction of the May timetable.

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

The May timetable is a big timetable change. It is roughly four times larger than any previous change over recent years of such timetables. It was a six-monthly timetable change. It was a very big change that reflected the massive investment that has been going into the rail system and all the opportunities to create new services across the country. In those circumstances, the timetable change did not just affect Northern and Thameslink, it affected every train operation in the country. All those other train services around the country had interlinkages with the train services being run by Northern, Thameslink and other Govia Thameslink Railway services.

As a consequence, simply suspending the timetable was not possible, because all the other train operators had put in place their own driver rosters and driver training programmes for all the other services running across the rest of the country. Not introducing the May timetable at that point would have been a far worse and more disruptive solution. This is progress. We recognise that there is significantly more to be done. We want to get back to where we were meant to get to, which was the full introduction of the May timetable, as soon as we can, but we want to do that gradually and to reintroduce services as soon as we can, once the appropriate driver training has taken place.

How can we ensure this does not happen again? As I have mentioned, work has begun to set up the independent inquiry into the timetable, implementation and deliverability of future timetable changes. That will be chaired by an independent transport expert, the chair of the current independent regulator, the Office of Rail and Road, Professor Stephen Glaister. In parallel to the inquiry, the Department for Transport is assessing whether Northern met its contractual obligation—a subject which a number of hon. Members asked about—in the planning and delivery of this timetable change. We will carefully assess Northern rail’s planning, risk assessment and resilience in preparing for the May timetable change.

We are currently reviewing whether Northern is in contravention of the franchise agreement. If it is found to be so, it would be referred to the Department’s enforcement advisory panel. The purpose of that panel is to review any contraventions of the franchise agreement fairly and consistently across all franchises. It will seek to respond in a consistent manner where different train operators commit similar contraventions, taking account of the Department’s enforcement policy and previous enforcement decisions, and will recommend the appropriate response, including any remedial plan or enforcement action, if required.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

Will the Minister set out a timetable for that? I think passengers have a real interest in knowing what timetable that scrutiny will cover.

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

Work has been underway over the last few weeks on this question, and we expect to come to a conclusion as soon as is reasonably possible.

In assessing whether Northern has breached its franchise agreement, it is important to bear in mind that there are other players in this story and Network Rail is an important one. While bearing in mind Network Rail’s failure to deliver the infrastructure I mentioned on time, I want hon. Members to be assured that we will hold the operator to the terms of its contractual obligations.

I want to give the hon. Member for Bolton North East a chance to wind up at the end. I thank all colleagues for their contributions. I remind them that once this phase has been completed, passengers on Northern will benefit from 1,300 extra services a week. Rail users of Northern have much to be hopeful about in the future of their rail services. Brand-new trains will soon be introduced, building on the improvement to timetables and stations already made in recent years. We are working closely with train companies to drive down cancellations and will support Network Rail and the wider industry in delivering these significant improvements.

Draft Welsh Ministers (Transfer Of Functions) (Railways) Order 2018

Debate between Lord Johnson of Marylebone and Rachael Maskell
Monday 23rd April 2018

(6 years ago)

General Committees
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

I will not be drawn on the procurement decisions for HS2 at this point. The point I wanted to make, and made, was that the bi-mode trains on this stretch of the network will deliver substantially the same benefits for passengers that electrification would, at considerably better value for money.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

I am grateful to the Minister for that answer, but does he agree that it will not provide equivalence to electrification on that part of the network?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

Clearly it will not be the same as electrification, because it will not require the disruptive works overhead, the gantries and so on, which would have affected passenger journeys. The introduction of the new bi-mode trains will, however, deliver substantially the same passenger benefits and, as I said in response to the hon. Member for Carmarthen East and Dinefwr, at considerably better value for taxpayers.

--- Later in debate ---
Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

My hon. Friend is exactly right. Once the whole of the new fleet is introduced and electrification to Cardiff is complete, passengers will benefit from a 40% increase in the number of seats in the morning peak and significantly better journey times between Swansea, London and other stations along the route, which will be about 15 minutes shorter than they currently are.

TEN-T was mentioned. It recognises strategic transport routes in the EU. It is not clear at this point how TEN-T will be treated post Brexit, but that will become clearer in coming weeks. As I said, the devolution of these rail powers is an example of close and effective co-operation between the UK and Welsh Governments.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

I am grateful to the Minister for giving way one more time. Will he acknowledge that the devolution deal in place here is less than the deal with Scotland? Can he explain why it is that the Welsh Government will not have full power over the future of its economy as well as serving the passengers of Wales?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

We are committed to devolution, and to the devolution process, but we do not want to go, in one small bit of secondary legislation, beyond the consensus that was agreed during the St David’s Day process. That needs to be considered as part of a coherent look at devolution settlements in the future.

Like hon. Members, I want to see improved rail services for passengers in England and Wales. I hope that hon. Members will agree that the devolution approach we have chosen recognises the inherently joint nature of a significant proportion of the Wales and Borders franchise, and ensures that the current extensive cross-border links can be maintained and developed for the benefit of passengers and the Welsh and English border economies. We will continue to support the Welsh Government to enable them to achieve the successful procurement of the next franchise. I commend the draft order to the Committee.

Question put and agreed to.

Resolved,

That the Committee has considered the draft Welsh Ministers (Transfer of Functions) (Railways) Order 2018.

Cotswold Line Upgrades

Debate between Lord Johnson of Marylebone and Rachael Maskell
Wednesday 28th March 2018

(6 years ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Lord Johnson of Marylebone Portrait The Minister of State, Department for Transport (Joseph Johnson)
- Hansard - -

I congratulate my hon. Friend the Member for Witney (Robert Courts) on securing the debate and providing us with an opportunity to discuss upgrades to the Cotswold line. As always, he and my hon. Friend the Member for Mid Worcestershire (Nigel Huddleston) have demonstrated their hard-won reputations as extremely focused and dedicated constituency MPs.

All rail services in Witney are provided by Great Western Railway under the Great Western franchise. The debate is timely, as the hon. Gentlemen noted, because it is a little more than a month since the conclusion of the Department for Transport consultation on the future of the franchise. I am delighted that we received more than 800 responses, demonstrating the importance that passengers and stakeholders attach to rail services. The Department is analysing the considerable volume of responses and will respond later this year.

My hon. Friend the Member for Mid Worcestershire, with the support of our colleague my hon. Friend the Member for West Worcestershire (Harriett Baldwin), raised the question of splitting the franchise. I should like to emphasise that, at this point, the Department has made no decisions. Any decision in favour of such a split would need to be made on the basis of real benefits, including to passengers.

It has been suggested that Cotswold line services could be split off to the operator as a separate franchise, with comparisons being drawn with the Chiltern Railways franchise. Such a comparison is not straightforward, and certainly not as straightforward as it would seem on paper—the Chiltern franchise operates close to 10 times as many train services as those on the Cotswold line. Having said that, the Department will look at all suggestions made in response to its consultation. I am grateful for the thoughtful way in which my hon. Friends made those suggestions.

Billions of pounds are being spent to upgrade services for passengers on the Great Western franchise. They aim to improve significantly the services experienced by a hundred million passengers a year, serving them all the way from London to Penzance and from Portsmouth to Worcester. The improvements will include brand new electric and bi-mode trains that will provide many more seats and more comfortable journeys, while timetable changes will mean faster and more frequent trips on many routes by 2019. The new intercity express trains have started operating on the Cotswold line, replacing the older high-speed trains and other types of train. The same trains will operate all fast services between Oxford and London Paddington, complementing those operating on the Cotswold line, ensuring through services on 125 mph trains, even though it has been necessary to defer electrification of the line north of Didcot to Oxford.

The Government have decided to extend the franchise, as the hon. Member for York Central (Rachael Maskell) noted, for the current operator GWR until March 2020, to make sure passengers get the best possible service while these upgrades are carried out. The Department for Transport will seek to agree terms for GWR to continue operating until 2022, which will allow the improved services to bed in fully before running a competition for a new long-term franchise.

On the future of the Cotswold line, in his response to the Department’s consultation, my hon. Friend the Member for Witney made many detailed comments about what he considers should be the priorities for the development of the route. Given how Hanborough has developed as a key access station for fast-growing communities in west Oxfordshire such as Witney, he focused on the developments and the train services he rightly would like at that station. Today, six services from Hanborough arrive at Oxford in the morning peak. He argues for an even more frequent service. He rightly recognises the importance of science to the economic development of the area by asking for some trains to run direct on a reopened route to Cowley, serving the important area around the Oxford science park. Those improvements and others highlighted in his response to the Department’s consultation would require substantial further development of the rail infrastructure in the area, as he noted.

I have seen with interest the formation of the north Cotswold line taskforce, which brings together a wide range of interested parties along the whole route. It would have seemed incredible 20 years ago to aim for a half-hourly service with far shorter journey times. That could be made possible only by a combination of the infrastructure upgrades we are putting in place, including further redoubling of the remaining sections of single track, and the division of the train service into a new regular express service supplemented by slower trains that stop at the smaller stations. I am particularly struck by how the taskforce thinks creatively about financing options and does not simply assume that the only feasible option is more Network Rail control period spending.

The taskforce’s work and my hon. Friend’s response to the Great Western consultation also highlight that rail is seen as a real and valuable alternative to the car. He put centre stage in his concerns the regular serious congestion on the A40 and other roads in his constituency, and rightly addressed modal shift.

Those who have attended recent rail debates will know that the Government are careful to ensure that they do not commit too early to specific projects in Network Rail’s control period 6, which starts in April 2019. I cannot commit at this stage to the project that my hon. Friend advocated so powerfully, because the control period 6 process remains under way, as does the rest of our analysis of responses to the Great Western consultation.

Elsewhere in my hon. Friend’s reply to that consultation, he raised the prospect of a new station at Yarnton in his constituency. I referred to the Department’s new rail strategy, “Connecting people”, which was published in November last year, which makes it clear that, as with the reopening of lines, a strong business case needs to be demonstrated where Government funding is sought for new facilities. The Government will consider proposals on a case-by-case basis, based on the economic benefits put forward by local partners.

My hon. Friend also mentioned the Tackley station crossing. The debate has focused mostly on train services, but that crossing is important. It is a passenger level crossing on a busy cross-country route with many passenger and freight trains, and it is used not just by users of the station, but by locals who want to cross the line and walkers who want to access the Oxford canal walk and the Oxfordshire way. As he mentioned, some years ago it was the site of the tragic death of a user. I recognise that it is not the easiest location at which to provide a safer alternative that is as accessible for all users, but we are encouraging Network Rail and local users to engage in a constructive dialogue so that we can find an acceptable outcome.

Hon. Members raised the issue of operational performance, which is obviously a critical question for passengers. When the Secretary of State announced the control period 6 funding for Network Rail last July, he put particular focus on better performance. The Government are determined that the railway should become more focused on issues that matter most to passengers, including punctuality and reliability. A more reliable railway would play a critical role in underpinning economic growth and bringing the country together, which is why the Government are committed to taking action to achieve those outcomes. My hon. Friend expressed forcefully the rising concern among his constituents about the level of cancellations on some GWR routes. It is critical that GWR does everything it can to minimise disruption to services and to address passenger concerns when services are cancelled.

On my hon. Friend’s points about integration and a more holistic approach to public transport, I draw hon. Members’ attention to the smart ticketing initiatives that are under way. Those projects have considerable potential to promote cross-modal use and intermodal shift more broadly. A GWR scheme is in place, and we are looking to develop that more broadly across the country.

Rachael Maskell Portrait Rachael Maskell
- Hansard - - - Excerpts

Will the Minister update the House on progress on smart ticketing? I am sure all passengers are interested in that.

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

I am happy to update the hon. Lady. Good progress continues to be made on the smart ticketing initiative, and we continue to hope that the smart ticketing system will be in place in full across the network by the end of the year. That is our objective, and it is crucial to ensuring that we get all the benefits that modern technology offers our rail system.

Overall, rail users in Witney and Mid-Worcestershire have much to be hopeful about. Brand new trains are already being introduced, building on the improvements to timetables and stations in recent years. The Cotswold line has come a long way in the past 25 years, but there is clearly considerable potential for it to be further upgraded and developed. My hon. Friend the Member for Witney and groups such as the Cotswold Line Promotion Group and the north Cotswold line taskforce are powerful advocates for change and improvement. Between them, they have an exceptional record of achievement on behalf of the travelling public. The Cotswold line deserves the best possible rail service, which is what the Department is determined to provide.

Student Maintenance Grants

Debate between Lord Johnson of Marylebone and Rachael Maskell
Tuesday 19th January 2016

(8 years, 3 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

There is an immediate grant saving of £2.5 billion, which comes directly off the budget deficit. As I just mentioned, there is of course the prospect down the line of some loans not being repaid, as a result of a conscious decision by the Government to invest in the skills base of the country and to allow people to pursue incomes that do not enable them to pay off the full value of the loan. The economic value of the savings, as I just said, is £800 million a year in a steady state.

I challenge the Opposition to explain how they would fund their alternatives. I note that the Labour party has in the past year put forward competing higher education funding policies, although they share one significant feature: their huge cost to the taxpayer. Labour’s leader, the right hon. Member for Islington North (Jeremy Corbyn), said in July that fees should be removed completely, with grants retained in full. The policy was costed by Labour itself at £10 billion. Such policies move us backward. They are unsustainable and, at a conservative estimate, would add more than £40 billion to the deficit over a five-year Parliament. We should be clear about what the results would be: more reckless borrowing, more taxes on hard-working people, and the reintroduction, inevitably, of student number controls. We have lifted student number controls and we will not allow the Labour party to reimpose a cap on young people’s aspirations.

I will deal with the risks associated with this policy as set out in the equality analysis, but let me first quickly respond to the false accusation that we refused to publish the assessment until prompted to do so by the National Union of Students. That is simply not true. Every year, when the Education (Student Support) Regulations 2011 are amended, an equality analysis covering the changes is published on gov.uk. This is standard practice. On 14 September, in a written response to a parliamentary question asked by my hon. Friend the Member for Totnes (Dr Wollaston), I said:

“The Government expects to lay amendments to the Education (Student Support) Regulations 2011 later this year and publish an Equality Analysis when the Regulations are laid. The Equality Analysis will include an assessment of potential impacts of the changes.”

Only on 22 September 2015, more than a week after that answer was given, did the NUS give notice that it would seek legally to challenge our policy. There has been no evasiveness in the presentation of the policy or its potential impacts.

I will deal now with some of the issues identified in the equality analysis and how they will be mitigated. Let it be remembered that similar issues were identified as a result of the 2012 reforms, but did not crystallise. Indeed, we now have a world-class higher education system, with record numbers of disadvantaged students in higher education, the highest rates of BME participation in higher education and more women in higher education than ever before. Our impact assessment explains that the risks will be mitigated by at least three factors, including the 10.3% increase in the maximum loan for living costs, the repayment protection for low-earning students and the high average returns on higher education.

More funding is also being provided through access agreements: in 2016-17, £745 million is expected to be spent by universities through access agreements, up from £404 million in 2009-10. That is money that makes a real difference to disadvantaged students, and we will of course monitor the progress of the policy through the data available from the Higher Education Statistics Authority and the Student Loans Company.

Rachael Maskell Portrait Rachael Maskell (York Central) (Lab/Co-op)
- Hansard - - - Excerpts

At the University of York, 40% of students get a maintenance grant. What assessment has been made of the impact on universities of not attracting students because they simply cannot afford to attend?

Lord Johnson of Marylebone Portrait Joseph Johnson
- Hansard - -

As I have already said, we are making a record amount of financial support available to students, and students from the poorest backgrounds will benefit from a 10.3% increase in financial support. They will have more cash in their pockets than ever before.

I hope that I have been able to clarify some of the misconceptions about our policy, the steps we are taking to increase living costs support and the process surrounding it. I will finish by directing Labour Members’ attention to the interview with Ed Balls in Times Higher Education this week, which should be of interest to them. He said that the

“blot on Labour’s copybook”

was that

“we clearly didn’t find a sustainable way forward for the financing of higher education”.

He went on to say:

“If they”—

the electorate—

“think you’ve got the answers for the future, they’ll support you”.

We have a plan for the future. In a time of fiscal restraint, we are taking action to ensure that university finances are sustainable, so that more people than ever before can benefit from higher education.