To match an exact phrase, use quotation marks around the search term. eg. "Parliamentary Estate". Use "OR" or "AND" as link words to form more complex queries.


Keep yourself up-to-date with the latest developments by exploring our subscription options to receive notifications direct to your inbox

Written Question
National Grid: Scotland
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department’s latest estimate is of the completion date of substation works associated with the Beauly to Denny transmission upgrade.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

Transmission Owners are responsible for delivering transmission projects and are regulated by Ofgem. Ofgem monitors delivery against agreed regulatory delivery dates and holds Transmission Owners accountable for the efficient and timely delivery of network upgrades. The licence delivery date for Beauly to Denny including the substation works is 31/12/2031. Government is taking action to accelerate the build out of electricity network infrastructure, through reforms to planning, regulation, strategic networks planning, unlocking supply chains and taking a strategic approach to workforce and skills.


Written Question
National Grid: Kent and Suffolk
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department’s latest estimate is of the completion date of the Sea Link transmission reinforcement project.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

Transmission Owners are responsible for delivering transmission projects and are regulated by Ofgem. Ofgem monitors delivery against agreed regulatory delivery dates and holds Transmission Owners accountable for the efficient and timely delivery of network upgrades. The licence delivery date for Sea Link is 31/12/2031. Government is taking action to accelerate the build out of electricity network infrastructure, through reforms to planning, regulation, strategic network planning, unlocking supply chains and taking a strategic approach to workforce and skills.


Written Question
National Grid: Construction
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department’s latest estimate is of the completion date of Eastern Green Link 1.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

Transmission Owners are responsible for delivering transmission projects and are regulated by Ofgem. Ofgem monitors delivery against agreed regulatory delivery dates and holds Transmission Owners accountable for the efficient and timely delivery of network upgrades. The licence delivery date for Eastern Green Link 1 is 31/12/2028. Government is taking action to accelerate the build out of electricity network infrastructure, through reforms to planning, regulation, strategic network planning, unlocking supply chains and taking a strategic approach to workforce and skills.


Written Question
National Grid: Yorkshire and the Humber
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department’s latest estimate is of the completion date of the Yorkshire GREEN project.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

Transmission Owners are responsible for delivering transmission projects and are regulated by Ofgem. Ofgem monitors delivery against agreed regulatory delivery dates and holds Transmission Owners accountable for the efficient and timely delivery of network upgrades. The licence delivery date for Yorkshire Green is 31/12/2028. Government is taking action to accelerate the build out of electricity network infrastructure, through reforms to planning, regulation, strategic network planning, unlocking supply chains and taking a strategic approach to workforce and skills.


Written Question
Clean Energy
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what discussions she has had with the National Energy System Operator on the deliverability of Clean Power 2030 since taking office.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

The Secretary of State speaks to the National Energy System Operator on a regular basis on a range of topics.


Written Question
National Grid: Construction
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department’s latest estimate is of the total capital cost of the transmission network upgrades required to deliver Clean Power 2030.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

Ofgem estimates that transmission owners will invest up to around £70 billion in Great Britain's electricity transmission network between 2025-26 and 2030-31. The majority of this spend remains subject to further in-period approval.

As well as supporting delivery of Clean Power 2030, this will accommodate growing electricity demand and reduce network constraints resulting from generation build having historically outpaced network build. Some expenditure also reflects essential asset replacement and maintenance.

Government monitors the progress of transmission projects required to meet our goal of clean power through regular engagement with industry and regulators. Cost estimates for individual projects are developed and maintained by the relevant transmission owners and are subject to regulatory scrutiny by Ofgem. Transmission owners are only permitted to recover costs that Ofgem determines are efficiently incurred.


Written Question
National Grid: Construction
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department’s latest estimate is of the completion date of Eastern Green Link 2.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

Transmission Owners are responsible for delivering transmission projects and are regulated by Ofgem. Ofgem monitors delivery against agreed regulatory delivery dates and holds Transmission Owners accountable for the efficient and timely delivery of network upgrades. The licence delivery date for Eastern Green Link 2 is 31/12/2030. Government is taking action to accelerate the build out of electricity network infrastructure, through reforms to planning, regulation, strategic network planning, unlocking supply chains and taking a strategic approach to workforce and skills.


Written Question
National Grid: Construction
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department’s latest estimate is of the completion date of Eastern Green Link 3.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

Transmission Owners are responsible for delivering transmission projects and are regulated by Ofgem. Ofgem monitors delivery against agreed regulatory delivery dates and holds Transmission Owners accountable for the efficient and timely delivery of network upgrades. The licence delivery date for Eastern Green Link 3 is 31/08/2034. Government is taking action to accelerate the build out of electricity network infrastructure, through reforms to planning, regulation, strategic network planning, unlocking supply chains and taking a strategic approach to workforce and skills.


Written Question
Clean Energy
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what estimate she has made of the (a) number of transmission projects identified by the National Energy System Operator as essential to Clean Power 2030 that are on track for delivery by end of 2030 and (b) level of grid decarbonisation achievable by that date.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

We work closely with the TOs on delivery of network projects, including identifying opportunities to accelerate delivery. As of 31st March, 64 of the 68 wider network projects identified by NESO as essential for CP2030 delivery are forecast to deliver by the end of 2030. We know that a clean power system is achievable, and the best way to protect consumers from fossil fuel price volatility.


Written Question
National Grid: East of England
Wednesday 16th September 2026

Asked by: Andrew Bowie (Conservative - West Aberdeenshire and Kincardine)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department’s latest estimate is of the completion date of the Norwich to Tilbury transmission upgrade.

Answered by Michael Shanks - Minister of State (Department for Energy Security and Net Zero)

Transmission Owners are responsible for delivering transmission projects and are regulated by Ofgem. Ofgem monitors delivery against agreed regulatory delivery dates and holds Transmission Owners accountable for the efficient and timely delivery of network upgrades. The licence delivery date for Norwich to Tilbury is 31/12/2031. Government is taking actions to accelerate the build out of electricity network infrastructure, through reforms to planning, regulation, strategic network planning, unlocking supply chains and taking a strategic approach to workforce and skills.