To match an exact phrase, use quotation marks around the search term. eg. "Parliamentary Estate". Use "OR" or "AND" as link words to form more complex queries.


Keep yourself up-to-date with the latest developments by exploring our subscription options to receive notifications direct to your inbox

Written Question

Question Link

Thursday 1st May 2014

Asked by: Andrew Bridgen (Independent - North West Leicestershire)

Question to the Department for Transport:

To ask the Secretary of State for Transport, how many High Speed 2 consultation requests are EIA development as defined in the Town and Country Planning (Environmental Impact Assessment) Regulations 2011; and how many recommendations for refusal of the grant of planning permission are (a) EIA and (b) non-EIA development.

Answered by Robert Goodwill

Safeguarding directions for the London to West Midlands section of HS2 were made in July 2013 and updated in October 2013. The number of High Speed 2 consultation requests which are EIA development as defined in the Town and Country Planning (Environmental Impact Assessment) Regulations 2011 is 5.

The number of recommendations for refusal of the grant of planning permission are as follows:

(a) EIA - 3

(b) non-EIA development – 3


Written Question

Question Link

Thursday 1st May 2014

Asked by: Andrew Bridgen (Independent - North West Leicestershire)

Question to the Department for Transport:

To ask the Secretary of State for Transport, how many (a) EIA and (b) non-EIA development recommendations HS2 Ltd has made for conditions to be imposed on planning permission to protect the High Speed 2 project.

Answered by Robert Goodwill

Following the making of safeguarding directions for the London to West Midlands section of HS2 in July 2013 (updated October 2013) , the number of recommendations made by HS2 Ltd for conditions to be imposed on planning permission to protect the High Speed 2 project is as follows:

a) EIA recommendations – 0

b) Non-EIA recommendations - 7