Thursday 13th October 2011

(12 years, 7 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Kelvin Hopkins Portrait Kelvin Hopkins (Luton North) (Lab)
- Hansard - - - Excerpts

I am grateful to have an opportunity to speak in this debate and congratulate the hon. Member for South Northamptonshire (Andrea Leadsom) on introducing it. We have had debates on the subject before in Westminster Hall, and I shall have to make some of the points that I made in those debates again, because they are significant.

I am a passionate believer in railways and have been for decades. Even when railways were unfashionable, I believed that they were the transport mode of the future, and so they have proved to be. Indeed, there is absolutely no doubt that we will have more railways in future. I believe that we should invest heavily in railways and in additional routes, but I remain a sceptic about HS2. I applaud in particular the speeches by the hon. Member for Banbury (Tony Baldry)—who has just left the Chamber—and my hon. Friend the Member for Birmingham, Hall Green (Mr Godsiff), who made many important points that I will not necessarily repeat.

The scheme is expensive, but if it was worth while I would support that expense. It also has an opportunity cost: we should be doing things now, not in decades to come. As the hon. Member for South Northamptonshire said, even getting on a train to Milton Keynes is a problem now, let alone finding a seat, and the same is true elsewhere. We need heavy investment in all sorts of railway schemes, but not necessarily this one, which will come a long time in the future, not now. However, it will not be necessary even in the future. The point has been made about Britain being a densely populated country, and many towns that need to be served by high-speed trains would not be. My hon. Friend the Member for Coventry North West (Mr Robinson) is quite right that he would not benefit at all from HS2. Indeed, getting to and from the station is a much more significant problem for those living even on the outskirts of Birmingham than getting from Birmingham to London.

We need more capacity, but for that we need to upgrade existing routes. For example, there is no question but that the east coast main line needs to be upgraded; indeed, I had a long talk about that with the chief executive at our recent conference. However, all we need is an additional viaduct to quadruple the track at Welwyn, a passing loop at Peterborough and a crossover at Newark, and then we will have no problem at all with 140 mph trains running from London to Edinburgh. To build a high-speed line carrying no more than two or three trains a day that far would be nonsense. We have the capacity now, provided we upgrade the route a little.

Anne Main Portrait Mrs Anne Main (St Albans) (Con)
- Hansard - -

I completely concur with the hon. Gentleman. The same train line goes through our constituencies. I also agree with my hon. Friend the Member for South Northamptonshire (Andrea Leadsom) that we should be looking at many other areas in which to invest. We could move many more passengers around the country. The hon. Gentleman is making a perfect argument for looking at this matter again.

Kelvin Hopkins Portrait Kelvin Hopkins
- Hansard - - - Excerpts

I thank the hon. Lady for her support. We have neighbouring constituencies and share the rail route that runs through our towns.

In the end, the problem comes down to the west coast main line, which needs the signalling to be upgraded to the most modern standard, more train paths, and to get the freight off the line. Freight and passengers do not mix. Freight trains move more slowly, and they damage the track more than the lighter passenger trains, so we need to invest in a dedicated freight line running up the backbone of Britain, from the channel tunnel to Glasgow, linking all the major conurbations. I have supported that scheme for a long time, and it would take 5 million lorries a year off the roads, as well as removing all the freight traffic from the east and west coast main lines. The passenger routes need to be separated from the freight routes and upgraded to improve capacity. I believe that that is what we need, and that is why I am sceptical about the HS2 scheme.

That freight route could be built in four years for as little as £6 billion, and it would cause no environmental difficulty because it could use existing under-utilised routes and old track bed could be brought back into use. That, and a couple of tunnels, would make the whole thing work. I have made this case time and again in the Chamber over the past 14 years, and I have mentioned it to the Minister of State. I have presented a paper on it to the Transport Select Committee. I also know engineers who have worked on the scheme and worked the details out. It just needs to be done. Fifteen of us had a meeting with the Secretary of State for Transport in the previous Government to put our case for the scheme, but the Department was so hostile because a small section of our proposed route overlapped the route it wanted to use for HS2. Even if HS2 is built, the lines could be paralleled at that point. There would not be a problem.

We need a freight route that is capable of taking full-scale lorry trailers on trains. That could never be done on existing routes without incurring the prohibitive cost of raising all the tunnels and bridges throughout the network. We need a track that has the capacity to take double-stack containers. Most of our existing routes cannot even take standard 9 feet 6 inch containers. We also need a track that has the capacity to take continental trains, which currently cannot get through our platforms because they are too wide, the gauge is too big. We need to be able to accommodate trains travelling from, say, Rome to Birmingham carrying San Pellegrino water.