High Speed Rail (London – West Midlands) Bill Debate

Full Debate: Read Full Debate
Department: Department for Transport

High Speed Rail (London – West Midlands) Bill

Geoffrey Clifton-Brown Excerpts
Wednesday 23rd March 2016

(8 years, 1 month ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Geoffrey Clifton-Brown Portrait Geoffrey Clifton-Brown (The Cotswolds) (Con)
- Hansard - -

I thank my right hon. and learned Friend for giving way on that point; I intervene because I had wanted to speak on this new clause but now will not have time. We heard cases in the Select Committee where it was quite clear that the lack of local valuers is doing an injustice to the people whose homes are being acquired. Does he agree that the Government must put that injustice right? The Select Committee made very strong recommendations about that aspect. This injustice must be put right.

Dominic Grieve Portrait Mr Grieve
- Hansard - - - Excerpts

I am so grateful to my hon. Friend. Yes, these are precisely the areas where Government intervention would be valuable. I urge my right hon. and hon. Friends on the Front Bench, even at this late hour, to give this careful consideration.

There is a similar story on the relationship with local authorities. Most of our local authorities, like all local authorities in this country, given the difficult conditions resulting from the continuing economic problems besetting our planet, are short of money to carry out important local projects. Therefore, the prospect of having their infrastructure ripped up during the construction process is inevitably a subject of legitimate concern to them. There is no proper reason why they and the local council tax payer should have to bear the end cost, of any description, on this project going ahead. Here again is an opportunity for my right hon. and hon. Friends on the Front Bench to beef this up and provide the necessary tools to ensure that HS2 honours these commitments.

I am no position to speak to HS2, and I do not understand why it has been so deficient in its approach to dealing with local communities, but that is the reality. I note from the Public Administration Committee’s most recent report that HS2 says that it has learnt its lessons and will do things differently in future. I very much hope that is the case, but until I actually see it with my own eyes and witness it from the comments of my constituents, I have reason to continue to doubt that that will in fact happen. That is all the more reason why these amendments, which are straightforward and should not add to HS2’s costs, or indeed to the burden of carrying out the project, ought to be accepted.

--- Later in debate ---
Andy McDonald Portrait Andy McDonald
- Hansard - - - Excerpts

That point has been raised several times. The intention, as expressed in the documents, is to have a pedestrian connection between them.

An overarching approach to an integrated station would not only take account of all the anticipated works but achieve the objectives of securing the best possible outcomes for the residents of Camden and minimising the enormous disruption they will undoubtedly suffer. Many properties will be demolished and other properties will be in extremely close proximity to the works; public open spaces will be lost; there will be fleets of heavy goods vehicles and commercial vehicles; and noise pollution will undoubtedly disrupt the peaceable enjoyment of many properties, including in places such as Cobourg Street, which is a tranquil community with a quiet courtyard at its heart, notwithstanding its close proximity to busy traffic and the railway station. Businesses in streets like Drummond Street will also be disturbed.

We are asking the good people of Camden to put up with a great deal and to make huge sacrifices for the benefit of the nation, and Labour has tried to do all it can, in new clause 22 and in Committee, to mitigate the impact on the quality of life for residents. We acknowledge the sincerity of the Minister and his colleagues in working to that objective, but we take the view that this is so important that the assurances given ought to be in the Bill and have the full force of law.

We seek to minimise the amount of excavated material and construction materials transported into and around the site by road and to have as much as possible moved by rail. Camden Council has developed a Euston area plan, and we propose that any designs for the enlarged Euston station take full cognisance of that plan and other such framework documents and relevant guidance. The assurances talk of various boards, including the Euston strategic board, the Euston station strategic redevelopment board and the Euston integrated programme board, which bring together a number of prescribed partners. We seek to ensure that the nominated undertaker—the relevant body carrying out the HS2 works—is obliged to participate in those boards, as the assurances given by HS2 so describe.

Geoffrey Clifton-Brown Portrait Geoffrey Clifton-Brown
- Hansard - -

Does the hon. Gentleman agree that if Euston station were holistically designed and developed, it would provide a huge opportunity for regeneration in the Euston area and produce a lot of good quality local affordable housing to replace some of the affordable housing that will be devastated by HS2?

Andy McDonald Portrait Andy McDonald
- Hansard - - - Excerpts

I agree entirely with the hon. Gentleman’s intervention. That is the thrust of our new clause, which I trust he will support. It stipulates that the redevelopment board will advise the Secretary of State on the delivery of an “integrated and comprehensive design” for the enlarged Euston station, and it is for the integrated programme board to make sure that the designs and construction plans for Euston fit with proposals for other Euston schemes.

Access is a real issue, so while the construction is under way, which it will be for many years, we want to ensure that pedestrians and cyclists have continuous access through the site, east to west and north to south, insofar as it is “reasonably practicable” to do so. A design panel will work to ensure that the relevant partners can agree an appropriate design. Whoever is appointed for these purposes by HS2 will be obliged to work with that panel to ensure full buy-in to the design. Indeed, there will be an obligation on the nominated undertaker to take proper notice of the recommendations made by the design panel, and if for some reason the nominated undertaker does not follow those recommendations, our new clause states that it will be required to explain why that is so. The new clause makes sure that the community is properly engaged throughout the construction works at Euston so that its concerns will be recognised and its voice heard.

The provision is even more important, given today’s publication of the Parliamentary and Health Service Ombudsman’s report on a complaint about HS2. It effectively concludes that there are fundamental problems with the way HS2 Ltd communicates with the residents affected by their plans and the way it handles complaints.

The report dealt with specific complaints, but it is worrying that the Chairman of the Public Administration and Constitutional Affairs Committee has said:

“There is still a culture of defensive communication and misinformation within this public body and that is not acceptable. Unless those responsible for delivering HS2 understand that first and foremost they serve the public, they will continue to be criticised for having complete disregard for the people, some of them vulnerable, who are impacted by this large-scale infrastructure project.”

--- Later in debate ---
Geoffrey Clifton-Brown Portrait Geoffrey Clifton-Brown
- Hansard - -

I was not expecting to be called, Madam Deputy Speaker, but I am delighted.

Having sat on the Select Committee, I wish to say two things, hopefully in less than a minute. First, the hybrid Bill Committee system needs overhauling: 160 days— not for me, as I joined only after the election—and 1,600 petitions is unsustainable. Somebody needs to look at the system. Finally, we should all celebrate the fact that we have a record number of people travelling on trains, but we need more capacity. I say to my right hon. Friend the Secretary of State, even though he did not acknowledge that I had been on the Committee, that we need to plan this thing properly. We must ensure that there is proper connectivity into HS2 from all the other lines and that the west coast main line and other lines can make the most of the opportunity for freight.