To match an exact phrase, use quotation marks around the search term. eg. "Parliamentary Estate". Use "OR" or "AND" as link words to form more complex queries.


Keep yourself up-to-date with the latest developments by exploring our subscription options to receive notifications direct to your inbox

Written Question
Gospel Oak-Barking Railway Line: Electrification
Monday 7th September 2015

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, what timetable is planned for the electrification of the Barking to Gospel Oak line; what forecast he has made of the cost of that electrification; and if he will make a statement.

Answered by Claire Perry

Network Rail proposes to deliver electrification of the Barking to Gospel Oak line by summer 2017, in time for the new four-car electric trains ordered by TfL to be introduced in 2018. Network Rail is still assessing the detailed cost of the electrification and gauge enhancement scheme between Thameshaven/Tilbury Docks and the Midland Main Line via Barking and Gospel Oak and the forecast cost will be provided to DfT in due course.


Written Question
Gospel Oak-Barking Railway Line: Electrification
Thursday 4th June 2015

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, when he expects work to (a) start and (b) be completed on the electrification of the Barking to Gospel Oak line.

Answered by Claire Perry

Enabling works are due to commence in October 2015, with major on site works due to commence in June 2016. Passenger services on the electrified route are due to be available for use by passenger operators by 30 June 2017.


Written Question
Gospel Oak-Barking Railway Line: Electrification
Thursday 4th June 2015

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, what funding has been allocated to Network Rail for the electrification of the Barking to Gospel Oak line.

Answered by Claire Perry

The Department for Transport and Transport for London have respectively allocated £90m and £25m towards the electrification of the line (2013 prices).


Written Question
Gospel Oak-Barking Railway Line
Thursday 12th March 2015

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, what progress has been made on the electrification of the Barking to Gospel Oak line; what the expected date of completion of that work is; and if he will make a statement.

Answered by Claire Perry

The detailed Network Rail GRIP 3 study of the engineering works required for electrification is expected to be completed in August. This will enable confirmation of cost, scope and delivery dates. The indicative completion date of Barking – Gospel Oak electrification is June 2017 with the electrified freight links to the route being complete by December 2018.


Written Question
London, Tilbury and Southend Railway Line
Monday 14th July 2014

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether the new trains due to be introduced during the new franchise agreement with NXET Trains Ltd for rail passenger services on the Essex Thameside line will equipped with accommodation for a train guard.

Answered by Stephen Hammond

The procurement of new trains is being carried out by NXET Trains Limited under European Union Procurement Regulations and has not yet begun. Decisions about this procurement are a commercial matter for the operator.


Written Question
London, Tilbury and Southend Railway Line
Monday 14th July 2014

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, how many new (a) automatic ticket gates and (b) ticket vending machines will be introduced at stations on the Essex Thameside route under the terms of the new franchise agreement with NXET Trains Ltd for rail passenger services.

Answered by Stephen Hammond

The standstill period for the Essex Thameside franchise competition has not yet concluded, as such the Department has not signed the new Franchise Agreement and we are not able to confirm this information at this time. An announcement will be made shortly once the Agreement has been signed. There is already a gate at every station on the franchise and all stations have Ticket Vending Machines (with the exception of West Ham, which is managed by Transport for London). Additional ticket validation will be provided at Dagenham Dock to support step free access at that station.


Written Question
London, Tilbury and Southend Railway Line
Monday 14th July 2014

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, what safeguards there are in the new franchise agreement on the Essex Thameside line with NXET Trains Ltd against unsafe reductions in staff over the life of the agreement.

Answered by Stephen Hammond

Staffing on the franchise is a matter for the operator. The operator must act within the regulatory environment of the railway, which includes safety obligations under their license to operate (granted by the Office of Rail Regulation).


Written Question
London, Tilbury and Southend Railway Line
Monday 14th July 2014

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, what discussions he has had with NXET Trains Ltd about minimum levels of (a) on-train, (b) station and (c) ticket office staffing levels in each year of the new franchise agreement for rail passenger services on the Essex Thameside line; and what current staffing levels are in each such category on the line.

Answered by Stephen Hammond

Staffing is a matter for the operator; as such no discussions have been held between the Secretary of State for Transport and NXET Trains Limited and minimum levels of staffing have not been specified.


Written Question
London, Tilbury and Southend Railway Line
Monday 14th July 2014

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, what discussions he has had with NXET Trains Ltd over plans to make staff more visible at stations on the Essex Thameside line during the term of the new franchise agreement for rail passenger services.

Answered by Stephen Hammond

The standstill period for the Essex Thameside franchise competition has not yet concluded, as such the Department has not signed the new Franchise Agreement and we are not able to confirm this information at this time. An announcement will be made shortly once the Agreement has been signed.


Written Question
Large Goods Vehicles: Driving Tests
Thursday 12th June 2014

Asked by: Jeremy Corbyn (Independent - Islington North)

Question to the Department for Transport:

To ask the Secretary of State for Transport, what training is given to driving examiners who test students in laden lorries.

Answered by Stephen Hammond

Potential large goods vehicle (LGV) examiners are required to hold the relevant driving licence entitlement for the category of vehicle they will be testing. In the case of laden lorries that is either category C or category CE.

Initial training courses last five weeks with a ratio of two trainees to each trainer. Courses emphasise health and safety issues connected with working practices, test centres and vehicles. The Driver and Vehicle Standards Agency (DVSA) conducts regular progress checks which culminate in a final test and end-of-course evaluation.

Since early 2010 some of the vehicles used to train examiners to conduct category C and CE practical driving tests have been loaded with independent bulk containers to simulate a lorry carrying a commercial load. Consequently during training all potential LGV examinersare trained and examined using loaded vehicles. Before 2010, some category CE training made use of concrete blocks on the trailer to simulate a load.

DVSA also delivers refresher courses for examiners who have not conducted LGV testing for six months or more which readdress the most important elements of the initial training course.