High Speed Rail (Preparation) Bill Debate

Full Debate: Read Full Debate
Department: Department for Transport

High Speed Rail (Preparation) Bill

Louise Ellman Excerpts
Wednesday 26th June 2013

(10 years, 10 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Louise Ellman Portrait Mrs Louise Ellman (Liverpool, Riverside) (Lab/Co-op)
- Hansard - -

I am pleased to support this legislation today, which is a significant step in securing High Speed 2. It is important to recognise that HS2 is about having a vision for the future. It is about making a much-needed step change in capacity on our railways. It is about meeting growing demand for rail, addressing congestion on our roads and motorways, and connecting major cities not just across this country and the UK, but potentially across Europe as well. It has the potential to rebalance our economy.

However, it is very important that progress on High Speed 2 does not go ahead in isolation from considering the importance of continuing to invest in the existing classic line. Existing improvements such as the northern hub and the electrification programmes must continue and be stepped up. Assurance must be given that there will be proper access to high-speed rail, and that means that more attention needs to be given to the siting of the stations and connections to them. It is important that no local services be reduced as a consequence of building the high-speed rail line, and it is extremely important that the potential of developing the freed existing lines for both freight and passengers be addressed. That means that more work needs to take place, perhaps through local authorities and local enterprise partnerships working together, to make sure that proper plans are worked out so that the existing lines freed when high-speed rail comes to fruition will be able to be used to the maximum for freight and for passengers.

It is also crucial that the potential for economic development and rebalancing the economy is achieved. That means that we must not make any assumptions that simply building a high-speed line will automatically bring those economic benefits. Work has to be done, again by the LEPs, with the local authorities and with Government support, to develop economic strategies, regionally as well as nationally, to support business in taking advantage of those opportunities. I was very interested to read the results of studies instigated by local authorities. The Core Cities study put forward by major cities in our country identified about 400,000 new jobs that would come as a result of high-speed rail, and Centro’s report, looking specifically at the west midlands area, identified about 22,000 jobs that would come. I emphasise that none of those jobs will come automatically; we need to give attention to economic strategies and support for business to make sure that those opportunities come to fruition.

A number of important issues must be addressed. Concern remains that under the Bill as proposed, high-speed rail may not go beyond Birmingham. We have heard assurances from Ministers but we need rather more than that; we need a commitment in the Bill to make sure that HS2 is not simply between London and Birmingham, and that the rail scheme progresses to Leeds, Manchester and beyond. The time scale is a very long one, even on the current proposals of 2026 to Birmingham and 2033 to Leeds, to Manchester and to other areas.

Lord McLoughlin Portrait Mr McLoughlin
- Hansard - - - Excerpts

I completely agree with the hon. Lady’s point. I wonder, Mr Speaker whether I might use this intervention to clarify something I said earlier, as I am afraid I gave the wrong figure. I said that the contingency was £12.7 billion but it is actually £14.4 billion, so it is larger than I said. I just wanted to take this opportunity, with your permission and that of the hon. Lady, to put the figure right.

--- Later in debate ---
John Bercow Portrait Mr Speaker
- Hansard - - - Excerpts

The House is grateful.

Louise Ellman Portrait Mrs Ellman
- Hansard - -

I thank the Secretary of State for clarifying that situation.

The consultation, which has not yet taken place across the whole of the proposed line, must be a very real one. A number of hon. Members have already told us of their local concerns. There are problems in relation to London and, in particular, the development around Euston station, which is an important and difficult issue. Hon. Members have also raised issues in the House relating to access to Stoke-on-Trent. The proposals for Liverpool are not good enough and need improvement. Important environmental issues need addressing, and the question of compensation has been raised in the House this afternoon. All those issues are vital and must be addressed in a reasonable way. It is important for them to be resolved successfully because that will help to deliver a successful HS2—high-speed rail that is about much needed capacity, connectivity and economic progress for the future, throughout this country and beyond.