Debates between Mark Pawsey and Luke Evans during the 2019 Parliament

A5 in the Midlands: Improvements

Debate between Mark Pawsey and Luke Evans
Wednesday 23rd March 2022

(2 years, 1 month ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Mark Pawsey Portrait Mark Pawsey
- Hansard - -

My hon. Friend anticipates my point. He is exactly right: we need to have an efficient road that enables growth to take place. One of the challenges of the A5 is that it is dualled in parts, but single carriageway in others. There currently appears to be no consistent approach to an upgrade, and we need that upgrade in order to achieve our local councils’ ambitious objectives for the area.

As part of the wider strategic road network, the A5 currently carries 23,000 vehicles a day on its busiest section, so it is a pretty hefty road. Sadly, however, and despite its increasing importance and usage, the A5 in the midlands has not seen a proportionate increase in funding to provide resilience and capacity. As my hon. Friend the Member for South Leicestershire (Alberto Costa) points out, if that is provided, it will enable the A5 to spearhead and safeguard sustained growth in the region.

The fear is that, if neglected, the A5 will act as a barrier to growth rather than an instrument of it. With investment, we believe the A5 can become a significant corridor for growth by enabling greater east-west connectivity, providing access to the M6 toll road, and supporting north-south movements through its strategic interchanges with other regionally important motorways, as I have already mentioned.

In its November 2018 A5 strategy document, the A5 Transport Partnership outlined three key strategic interventions that it argued would be required to unlock the potential of the area served by the A5, and they are relevant today. The first priority is to make improvements between the M42 and M69—a combination of online and offline dualling to deliver the first phase of the A5 expressway, providing expansion of the MIRA site, which sits between Nuneaton and Hinckley, and works associated with the construction of HS2 at junction 10 of the M42. That is the first priority.

The second priority is the part between the M69 to M1 and M42 to M6. Again, it would be a combination of online and offline dualling, but this time to deliver the second and third phases of the A5 expressway. A third objective is to make better use of the M6 toll road. Those of us who have used the M6 toll road will know that it is not to capacity. If we can improve the size, we can get more traffic off the M6 and on to the toll road. In addition to those key priorities, improvements are needed to enhance the A5’s connectivity to the wider strategic road network. I know there are proposals for a new junction 20A on the M1, to bring relief to junction 20 at Leicester, which is the junction between the M1 and M69. That will provide additional growth opportunities.

Ministers are aware of the need for investment, given that one of the third road investment strategy pipeline projects is the upgrade between junction 1 on the M69 and junction 10 on the M42, and I hope that the debate will further press the case to bring that scheme forward. By securing this much-needed upgrade of the A5, we can help deliver growth around the corridor route, support network resilience, ensure greater sustainability and safety, and manage the impact of freight on the road.

My hon. Friend the Member for South Leicestershire made some remarks about the economics, which I want to focus on. The 53-mile section between the M1 and the M6 plays a significant role in supporting the sub-regional economies of Warwickshire, Leicestershire, Coventry, Staffordshire and west Northamptonshire, and the economic performance of the A5 is strong when looked at in the light of the broader west midlands economy. As I mentioned, a number of important economic centres along that corridor will be subject to further expansion in coming years.

The MIRA enterprise zone is expanding; Magna Park in Leicestershire, in my hon. Friend’s constituency, is expanding; DIRFT 3 in Northamptonshire, which sits on the border of my constituency, is currently the subject of substantial construction; and Kingswood Lakeside Employment Park in Staffordshire—which I believe is close to my hon. Friend the Member for Stafford (Theo Clarke)’s constituency—is coming forward. In my constituency, we have a substantial residential development at Houlton and the Rugby Gateway mixed-use development. I hope I am building a case for why it is imperative that the A5 is upgraded, to ensure that its present constraints do not curtail this planned growth or act as a barrier to continuing inward investment.

It is worth pointing out that unemployment levels along this corridor of the A5 are currently lower than the UK average, and with the expansion of the economic hubs I have just referred to and the further employment opportunities that will bring, that situation will only improve. As well as supporting local economies, the road has a wider role in providing connectivity to other economic centres, such as the Oxford-Milton Keynes-Cambridge growth corridor. When we combine the housing growth with the economic growth and the increased employment opportunities, it is clear that the A5 will come under significant further pressure over the coming years.

Luke Evans Portrait Dr Luke Evans (Bosworth) (Con)
- Hansard - - - Excerpts

My hon. Friend is making a fantastic case for why the A5 is so important. Does he agree that one of the principal problems with the A5 are the boundaries of the districts, councils and administrations that it borders? That makes things hard, because people always see the A5 as a periphery. We have heard talk about the west midlands, the east midlands, Leicestershire and Northamptonshire, and that is part of the problem. It is so important that my hon. Friend has secured this debate to make sure the Government realise we can release this stricture across the centre of the UK between Wales, England and London, and that doing so would make a huge difference economically, but also to the daily lives of the people we represent.

Mark Pawsey Portrait Mark Pawsey
- Hansard - -

My hon. Friend is right. The road sits as the boundary—it is the boundary of my constituency, the boundary of Warwickshire, and a regional boundary—but the local authorities have come together pretty effectively to press this case. It would have been very easy for each authority to have tried to do its own thing, but as it is, a range of bodies, including those in the private sector, have come together to argue the case for improvement. The Government have been clear that they recognise investment in infrastructure is needed to improve productivity and economic growth. When it comes to the A5, I hope the Minister will be able to say positive words that will lead to action.

I will also say a word or two about the importance of the logistics sector. As I have mentioned, Rugby is part of the golden triangle, and my constituency has certainly benefited from its geographical location at the centre of England. It contains several large logistics businesses, which has driven economic growth in Rugby, provided many employment opportunities, and helped my constituency become one of the fastest-growing towns in the country. Rugby is home to such household names in the logistics industry as DHL and Hermes, and just over two years ago, Amazon took the decision to invest in Rugby by building one of its fulfilment centres on the outskirts of the town, near the A5 and its junction with the M6.

As well as the numerous employment sites in my constituency that benefit from the A5, there are numerous other large and strategic employment sites in B8 use, logistics and distribution along the route. I have already mentioned DIRFT, Magna Park and Kingswood Lake, but I will now also mention Sketchley Meadows in Hinckley and Birch Coppice in Tamworth. Previously, I have outlined the importance of the MIRA Technology Park, an enterprise zone that is of course vital to the resurgence of the automotive industry in the midlands; indeed, that manufacturing sector is synonymous with the west midlands.

All the sites that I have referred to are of strategic importance, with many in line for expansion as our region continues to attract investors who are either keen to locate in the west midlands or keen to develop their businesses in the west midlands further. I regularly hear from developers keen to invest along the corridor.

However, a real worry is that growth in investment will be inhibited unless we now take the decision to invest in our strategic transport network. We are fortunate in our location at the centre of England to have generally excellent access to the motorway network, but without further investment to build network capacity and resilience, there is a real danger that we will miss the opportunity to rev up the midlands engine in the way that we would all like.