Fire Safety Bill Debate

Full Debate: Read Full Debate
Department: Home Office

Fire Safety Bill

Meg Hillier Excerpts
2nd reading & 2nd reading: House of Commons
Wednesday 29th April 2020

(3 years, 11 months ago)

Commons Chamber
Read Full debate Fire Safety Bill 2019-21 View all Fire Safety Bill 2019-21 Debates Read Hansard Text Read Debate Ministerial Extracts
Meg Hillier Portrait Meg Hillier (Hackney South and Shoreditch) (Lab/Co-op)
- Hansard - -

Thank you, Madam Deputy Speaker.

I wish to start by declaring my own interest, in that I am a leaseholder in an affected block. Happily, the owner of my block has taken on all the costs of replacement but, like many of my constituents, and others up and down the country, I live in a property that is technically valueless at the moment. That is causing problems, which I will touch on, but I also want to use this opportunity to welcome my hon. Friend the Member for Croydon Central (Sarah Jones) to her place on the Front Bench. She has been a doughty campaigner on this issue in her previous portfolio, so it is great to see that she can continue to fight for all those up and down the country who are affected. I hope that the Minister will hear what I have to say, and what others have said, and answer these questions, some of which go a little beyond the Bill, because it goes only so far, as a short, three-clause Bill, and there are wider issues here.

The Bill is long overdue—it has taken a long while to get this far—not just because of the tragedy of the Grenfell fire three years ago, but because of changes over many years and, as others have highlighted, under different Governments, that led to weakness and confusion over who is responsible for fire safety in a block. That and recent developments have led to real misery for many leaseholders in my constituency and up and down the country. Such people are mortgage prisoners, trapped with expensive mortgage payments and valueless homes. They are therefore unable to sell or rent their properties out, and they are dealing with the costs involved, including those for a waking watch, which in many blocks means two people per block. That is very expensive, but these people are also dealing with the upheaval, and the fear of scaffolding and major works going on around their home, which makes it harder for them to have peaceful enjoyment of their homes.

As of March 2020, only 54% of social housing blocks had had their remediation works done and nearly 90% of private residential blocks still had work to be done. That means that overall three quarters of ACM blocks—266 blocks, mostly flats—have yet to have remedial work done. We have highlighted in debates beyond this one the need for experts to do this work, and with coronavirus we have hit another challenge, because we cannot bring in expertise from elsewhere. Coronavirus is also increasing cost, making it harder for contractors to do the work, which means more delays and yet more costs for leaseholders. This therefore has to continue to be a priority, even during the pandemic. I know that this is not the direct remit of the Minister, but the Bill, and particularly the secondary legislation that follows it, could play a part here.

In the Budget, the Chancellor set aside £1 billion to do this remedial work, but we know that that is not enough—we see that when we look at the Bill and the amount of work involved. It might be a 10th of what is needed, and there is still no clarity about who will bid for that money. The Home Office is responsible for fire safety, so it needs to work closely with the Ministry of Housing, Communities and Local Government to make sure that the money that is available is properly applied, easy to bid for and quick to be spent so that we make sure that these blocks get dealt with. The Home Office is responsible for fire safety, so if MHCLG does not have enough funds to help to deliver that, there will be ongoing problems.

I could raise many specific examples—I have raised them in the House before—but when there are owners with housing associations involved, there is double trouble, because there are leaseholders of the housing associations, and the HAs have a relationship with the owner or developer of the block. I want to highlight some of the tactics that can be in play and the delays that owners and developers can inflict on residents. I wish to highlight the case of Regal London, which built The Cube building in Hoxton. In the first year, when many residents were raising snagging issues, Regal did not respond. That lack of response has continued. There has now been five years—scaffolding has been up for a good couple of years—with residents still not sure what is going to happen and who is going to pay. In the meantime, the block has some fire safety issues, and with the to-ing and fro-ing between the owner and leaseholders, the resolution is not there.

While the Bill goes so far, there is a practical element to this, too. As we in this place know, legislation does not solve everything. While what needs to be done will be on the statute book, and that is a welcome beginning, there is a big practical job of making sure that the Bill is real, living legislation that delivers on the ground. While there are legal wrangles going on between owners and residents and organisations such as Regal, which is leading constituents a merry dance and not responding very well, this causes a problem. We know the costs for individuals are huge. I hope the Minister will, in Committee, be able to answer our questions on how this will practically deliver. It is a welcome first step late in the day. It is a start, but I hope that in Committee we will see discussion and movement on how this could be the beginning and not the end.