Planning and Infrastructure Bill (Fourth sitting)

Debate between Michael Shanks and David Simmonds
David Simmonds Portrait David Simmonds
- Hansard - - - Excerpts

I have a couple of questions. As my hon. Friend the Member for Hamble Valley has set out, we are broadly supportive of the direction of travel around energy in the Bill.

One of the things we are all conscious of with the move to renewables being the main source of power in the grid—something that the UK has achieved faster than most other countries, with a bigger drop compared with the 1990 baseline than any other developed economy —is that it makes the grid more complex. Unlike oil, gas and nuclear, which can be delivered in an entirely predictable manner, renewables are generally much less predictable. There are times when the wind does not blow and the sun does not shine, and we cannot therefore put that element into the grid. We need to find alternative methods so we need to be able to shift greater amounts of power around to meet the growing energy needs.

As the Minister has outlined, the regime that is envisaged will, for a limited period of time, give greater powers to the Government to determine who gets connected and in which order. First, will the Minister set out how he and the Government intend to feed back to Parliament what we learn from that process, to inform the future shape of our energy grid?

Secondly, what recourse will there be for those at a certain point in the queue who anticipate that their development, whatever it may be, will be served by a particular project and connected at a particular point, if the Government decide otherwise because the reordering of the queue is, in the Minister’s view, necessary? We all understand why that may happen, but if someone is about to invest in a major new carbon capture and storage facility—the sort of major infrastructure project that the Bill is designed to support—and they expect it to be powered by a wind farm but are then told they have been moved much further down the queue than they expected, that will affect the delivery of that project. It would be helpful to understand the process whereby those affected by the reordering of the queue are able to challenge the decision, if necessary, and certainly to engage with the Government, or with constituency MPs, who may seek to advocate for them, so that the reordering can be revisited if necessary.

Michael Shanks Portrait Michael Shanks
- Hansard - -

I thank the hon. Gentleman for those helpful questions. He rightly set out the fact that the grid is already considerably more complex than it was 20 or 30 years ago, and it will become more complex, which is partly why the reform of connections is so important.

The hon. Gentleman is right to say that the process of prioritising projects will mean that some will be deprioritised. We have looked at the projects that already have a connection date, and in many cases they will proceed. Viable generation projects above the capacity ranges outlined in the clean power action plan—the first strategic document that will be used to guide projects—might still be able to connect if there is capacity in that particular bit of the DNO after the prioritised projects have been assessed. If there is no space in the pre-2030 queue, they will be offered dates in the 2031-35 process.

We have been clear throughout that the process has not been arbitrary or theoretical. Ofgem and NESO have gone through individual applications that are currently in the process to make sure not only that they fit with the requirements of the clean power action plan but that projects are not unnecessarily disadvantaged. Some projects will go ahead even though they are not in the strategic plan, because where they already are in the grid will make it possible for them to go ahead.

The question of transparency is really important. I will come back to the Committee with details on how we might make the information public, but throughout the process Ofgem and NESO have made public as much information as possible about how they have gone about things, and there was a full public consultation as well. The point about how individual MPs can see whether projects in their constituency are affected is well made and I will take that away and reflect on it.

The critical fact, as the previous Government rightly recognised, is that 750-plus GW is simply unmanageable. Really good projects are sitting with dates long into the future but cannot connect because of what are often phantom projects that are never going to come to fruition and are holding up spaces in the queue. For all the reasons that the hon. Gentleman outlined in terms of the importance of energy security, and the importance of prioritising the queue, we think that the Government amendments and the clause are essential.

Amendment 41 agreed to.

Amendments made: 42, in clause 12, page 16, line 17, leave out

“as mentioned in subsection (1)(c)”

and insert

“in accordance with the conditions of an electricity licence”.

This amendment is consequential on amendment 41.

Amendment 43, in clause 12, page 16, line 22, after “distribution system” insert

“(and such an improvement may include changing the order in which connections are made)”.

This amendment clarifies that the purpose for which a direction may be given under clause 12 may include the making of changes to the order of the queue for connections to a transmission or distribution system.

Amendment 44, in clause 12, page 16, line 23, leave out subsections (4) and (5) and insert—

“( ) A direction under subsection (2) must describe the kinds of modification to be made by the person to whom it is given.”

This amendment inserts a new subsection which would mean that a direction made by the Secretary of State or the GEMA to the ISOP or an electricity distributor to modify an agreement must describe the kinds of modification required.

Amendment 45, in clause 12, page 16, line 38, at end insert—

“(7A) Before giving a direction under subsection (2), the relevant authority must consult—

(a) the person to whom it proposes to give the direction, and

(b) such other persons as the relevant authority considers appropriate.

(7B) Subsection (7A) may be satisfied by consultation carried out before the passing of this Act (as well as by consultation carried out after that time).

(7C) A relevant authority must publish details of any direction it gives under subsection (2) as soon as reasonably practicable after the direction is given.

(7D) A relevant authority may exclude from publication under subsection (7C) any information the publication of which would be likely to prejudice the commercial interests of any person.”

This amendment requires a relevant authority to carry out consultation before giving a direction under clause 12. It also requires a relevant authority to publish any direction it gives under the clause.

Amendment 46, in clause 12, page 16, line 41, at end insert—

“(8A) The power to give a direction under subsection (2) may not be exercised after the end of the period of three years beginning with the day on which this section comes into force.”

This amendment ensures that the power to give a direction under clause 12 is time-limited in the same way as the power to make modifications to licences and other documents under clause 9.

Amendment 47, in clause 12, page 17, line 10, at end insert—

“(11) In Schedule 6A to the Electricity Act 1989 (provisions imposing obligations enforceable as relevant requirements)—

(a) in paragraph 4A (electricity system operator), after sub-paragraph (c) insert—

‘(d) section 12(8) of the Planning and Infrastructure Act 2025 (duty to comply with direction under section 12 of that Act).’;

(b) in paragraph 5 (distribution licence holders), after sub-paragraph (g) insert—

‘(h) section 12(8) of the Planning and Infrastructure Act 2025 (duty to comply with direction under section 12 of that Act).’”—(Michael Shanks.)

This amendment amends Schedule 6A to the Electricity Act 1989 in order to provide for enforcement of the duty to comply with a direction given under clause 12.

Clause 12, as amended, ordered to stand part of the Bill.

Clause 13

Managing connections to the network: strategic plans etc

Question proposed, That the clause stand part of the Bill.

--- Later in debate ---
Michael Shanks Portrait Michael Shanks
- Hansard - -

As I think I have just outlined, that amendment did not just call for the money to make the system more efficient; it called for it to be spent in communities on community benefits. That is quite different. My argument to the shadow Minister in resisting that amendment was that we did not want to tie the hands of the Scottish Government, because we see that investing that money in making the planning system more efficient is probably the best use for it, but it is not for me to tell them that. This clause is about giving them the power to set and charge fees to electricity network operators. I suggest that the point he is making is a slightly different one, but if I have misunderstood him, perhaps he can explain.

David Simmonds Portrait David Simmonds
- Hansard - - - Excerpts

A general point arises here, which we also debated on the Renters’ Rights Bill Committee. The different systems in Wales, Scotland, Northern Ireland and England—most of the legislation we are dealing with here is for Scotland, Wales and Northern Ireland—give rise to a risk of inconsistency. The shadow Minister spoke of the importance of community benefit. That is designed to secure community support. If there is a view that Ministers in Scotland might choose to spend such revenue on other things to the detriment of community benefit, that may also undermine consent.

I completely agree with what the Minister is saying about creating the necessary power, but will he commit to further discussions with his colleagues in the Ministry of Housing, Communities and Local Government so that we can ensure—not just in this Bill, but in future legislation—that where we expect a community benefit to derive from something that we decide on, it will be a consistent benefit across the UK?

Michael Shanks Portrait Michael Shanks
- Hansard - -

In general, I agree and disagree with the hon. Gentleman’s point. I understand the point he is making about consistency, but I take the view that the whole purpose of having different devolved Administrations in England, Wales and Scotland is to make different decisions. Northern Ireland is separate in the energy discussion, because it has a separate grid.

I am not sure that I would say that consistency at all costs is the right approach. We created the Scottish Parliament and the Welsh Assembly so that they could make decisions locally that affected them in a different way. We have worked with the Scottish Government on these changes to make sure that there is a package of reforms to the consent arrangements under the Energy Act that relates to the planning system in Scotland as it currently is. It is not the same starting point as the system in England and Wales, so it is important to look at them separately. Nevertheless, I understand the hon. Gentleman’s point.

I return to clause 17. Fees are already charged in England and Wales for processing wayleave applications. I reiterate—this comes back to the point made by the hon. Member for Broxbourne—that the Scottish Government do not have the power in legislation to raise those fees. That power is reserved. The clause will give them that power.

--- Later in debate ---
David Simmonds Portrait David Simmonds
- Hansard - - - Excerpts

We broadly support the content of clause 20, but I have one question for the Minister. I am mindful of his comments about the process of EU retained law, and it is absolutely right that we are looking to update that. However, a lot of the new powers set out for Scottish Ministers are the kind of thing that, in England, we would expect to be the subject of a pre-application consultation. One might ask the promoter of a project to come in and discuss those exact things with the local authority, the strategic planning authority if there is one, or the mayoral authority or the combined authority, so that the application process can be streamlined as much as possible.

Earlier on, we said that we would amend legislation through the Bill to remove that process in England. Given the intention to effectively introduce a top-quality process for applications to be considered in Scotland, does the Minister agree that there is an element of contradiction in that, in the same piece of legislation, we are seeking to remove many of the equivalent processes in England?

Michael Shanks Portrait Michael Shanks
- Hansard - -

I understand the argument, but it appears as a contradiction only if we assume that both planning systems are the same, which they are not. And they are not slightly different—they are fundamentally different. The processes are different. The timescales are different. The opportunities for public consultation are different throughout, so we are starting from a different starting point. Although I understand the hon. Member’s point, I do not think that the two are comparable.

This particular clause is even more narrow than the hon. Member recognised. It is simply about the assimilated regulations. I have been in a number of Delegated Legislation Committees where we have discussed some of the unintended consequences, as we obviously assimilated thousands of different pieces of legislation into UK law. As I say, the result was that neither the UK nor the Scottish Government currently have the power to amend these regulations, which is a ludicrous position for us to be in. This clause is narrow in scope, and I do not think it has quite the reach that the hon. Member is suggesting.

Question put and agreed to.

Clause 20 accordingly ordered to stand part of the Bill.

Ordered, That further consideration be now adjourned. —(Gen Kitchen.)