All 1 Nick Smith contributions to the Parliamentary Buildings (Restoration and Renewal) Act 2019

Read Bill Ministerial Extracts

Tue 21st May 2019
Parliamentary Buildings (Restoration and Renewal) Bill
Commons Chamber

2nd reading: House of Commons & Money resolution: House of Commons & Programme motion: House of Commons

Parliamentary Buildings (Restoration and Renewal) Bill Debate

Full Debate: Read Full Debate
Department: Leader of the House

Parliamentary Buildings (Restoration and Renewal) Bill

Nick Smith Excerpts
2nd reading: House of Commons & Money resolution: House of Commons & Programme motion: House of Commons
Tuesday 21st May 2019

(4 years, 11 months ago)

Commons Chamber
Read Full debate Parliamentary Buildings (Restoration and Renewal) Act 2019 Read Hansard Text Read Debate Ministerial Extracts
Meg Hillier Portrait Meg Hillier (Hackney South and Shoreditch) (Lab/Co-op)
- Hansard - - - Excerpts

It is a pleasure to follow the hon. Member for Caithness, Sutherland and Easter Ross (Jamie Stone) and to hear his wisdom. He is right that if we do not start by being open and honest about the challenges, we will be on a hiding to nothing. In that respect, the project has been bedevilled with problems, which I will touch on, but I hope that today, when it seems there is broad consensus for the Second Reading, we will be able to move forward.

I welcome the Bill and the personal determination of the Leader of the House to get it through. Her predecessors, for understandable reasons and the reality of politics, were a bit nervous about taking this forward, and there were challenges in getting the vote through in January 2018, but we are here today, with huge progress having been made, and I congratulate her on getting us to this point.

As the Leader of the House knows, this is just the beginning. I want to touch on the history—though that has been well covered by others; on the very real risks; and on the future plans, including the costs. I have the privilege of chairing the Public Accounts Committee. The right hon. Member for Gainsborough (Sir Edward Leigh) was one of my predecessors, and although we do not agree on every aspect of this issue, we absolutely agree that we need to watch taxpayers’ money very closely. As he rightly says, it is not other people’s money; it is the money our constituents work hard for and expect to be spent wisely.

As others have said, we have put this off for far too long. The hon. Member for Mole Valley (Sir Paul Beresford) talked about 1904; others talked about what happened 40 years ago. We have pushed this problem away for far too long. It is heartening that it was only seven years ago that the former Clerk of the House commissioned a survey to look at the matter. He feels that that is a long time, but in the grand scheme of things he should be congratulated because it has moved things on much faster than at any time in the previous many decades.

I had the privilege of looking at this on the Public Accounts Committee—I will touch on that and the finances a little later—and while serving on the Joint Committee under the chairmanship of the right hon. Member for Meriden (Dame Caroline Spelman). I thank her again for her stewardship of that Committee. We saw the shadow Sponsor Body at that time.

Others have talked about the risks. It is worth remembering that there have been 66 fires since 2008, as you will be aware, Mr Deputy Speaker. At any one time, there are eight fire wardens patrolling this building. As the Leader of the House said on the radio this morning, only at the end of last year there was one that could have been catastrophic, not for the whole building, but for a certain section of it. It was lucky that it happened during the week, because the patrol pattern must be a bit different at weekends. If it had happened at the weekend, it might not have been discovered so quickly.

My hon. Friend the Member for Rhondda (Chris Bryant), in eloquent fashion, highlighted the “big stink”. The big stink of previous times led MPs to decide that it was time to build a sewerage system for London, but we are now suffering our own big stink in parts of the building. It is not nice, it is not healthy, and it is really pretty terrible for the staff working in, particularly, the basement rooms who have to put up with it. We must keep remembering that it is the staff who matter.

Mice are rife in the building. Unlike the Leader of the House, I have not yet seen a mouse in my office, but men repeatedly crawl into the cavity above my office, which is close to the roof, and often, especially when I am here during a recess, I see men crawling into holes in different parts of the building such as the upper corridors. They are doing excellent work, and I applaud them for that, but I know that it is more expensive for them to do it at times when we are not here than it would be if we could decant. That is another reason why the Bill is so important. Of course, asbestos is also a huge problem, and one whose full extent we do not know at this point.

Future plans are critical, and even given the consensus here, different opinions have been expressed about what should happen next. It was heartening to speak to representatives of the Sponsor Body in the Committee, and I have had an opportunity to meet its chair, Liz Peace, on other occasions. She has made clear that its role must be to make it easier for us to make the decisions about how we work, but not to tell us how to do it. That would include ensuring that the building has a connectivity that will be future-proof. For example, we could, if we chose, have video booths instead of the phone booths that still exist across this place. The body could allow discussions about how we vote and how we operate, but could not impose them on us. A building shapes us, and, as we said in the Joint Committee, it is important that not just MPs and Members of the House of Lords but everyone—including the members of the public who use this building—is consulted about what they want to see.

The pressing issue, of course, is that of the mechanical and electrical “guts” of the building. Dealing with that will involve about 80% of the work, the bit that we shall never see. We shall come back, and it will have been sorted out. It currently costs several million pounds to remove all the wiring from a riser. The riser must be replicated outside the building while people inside, working in asbestos conditions, in shifts, in spaces the size of a small fireplace, remove all the old wiring and other equipment and replace it. That takes more than a year, sometimes two years, and, as I have said, it costs millions of pounds.

There is, however, a huge opportunity for us to renew this UNESCO world heritage site. The right hon. Member for Gainsborough made some important points. Like a number of other Members, he talked rather disparagingly about an IKEA Chamber. I do not think that we are seeking an IKEA Chamber, but I hear what those Members are saying. The “replica” Chamber has been portrayed as though it would be an exact replica of this place, but the plans are actually quite flexible. We have an opportunity to shape its future and decide how permanent it is: whether it can turn into something else later, or whether it can become an overflow, either permanently or as a flexible space. It is important for us to become involved in a positive way, and nail that now, so that eventually the Sponsor Body will be able to take over.

It is vital that we improve access for those with, for instance, mobility issues. The right hon. Member for Meriden touched on the issue of the frankly embarrassing loop system in this place. As a teenager, a member of my family was very embarrassed about admitting her deafness, and would have been mortified by the idea of coming to a building like this and having to wear what is effectively a big necklace with a clunky thing attached to it. She would not have felt able to participate. We need to be sensitive to the way in which we label people, as we currently have to do.

In fact, we were surprised to learn that there was a loop system. It was only because we had the privilege of serving on the Committee with Lord Stunell that we learned about it. Otherwise, we would never have known. I think of all the people who have visited the House during the 14 years for which I have been here, and whom I have never been able to inform about the loop because I simply did not know about it.

We also have an opportunity to use the “dead space” between buildings better. I think of the restoration of Hackney town hall, a beautiful 1930s building. Glassing over courtyards has provided a usable space while preserving the beauty and integrity of the building. When people talk about IKEA, we think of the light wood for which it is famous. When old buildings are restored—when workmen go back to the wood and re-polish it—it often turns out not to be dingy and dark, but a great deal brighter and lighter. However, it is a long time since that was done in this place.

Safety is, of course, critical. I sometimes joke, rather cruelly, that at least I am based near a stone staircase, but the reality of that cruel joke is that many staff are in little cubby-holes a long way from a proper fire exit route, and it is not acceptable that we have left it so long for them to be supported. We need to allow for smarter technology to be built in so we future-proof this building, and we need to think, as we allow the Sponsor Body and Delivery Authority to get on with it, about our vision for what we would like to see in this place: not tinkering with it every step of the way, not changing the business case and the plans once they are set in stone, but allowing that flexibility to be built in. We must also make it clear at the beginning if there are areas where we do or do not want to see big change.

There are huge opportunities to secure better access for visitors, and to make some money out of this building when we are not sitting. I work in the old Palace now thanks to the privilege of the office I hold; it provides me with a beautiful office. I get to see the House differently from when I was working in other parts of the building, and it is like the Mary Celeste in recess or on a Friday when Members are not around. There is an opportunity if we think flexibly to make sure this place is used more effectively by the very public we are here to serve.

The Bill Committee focused a great deal on the governance aspects. The Sponsor Body is critical because we effectively hold it to account for the money that will be granted for this project. Its chief executive, who is not yet appointed, will be the accounting officer. It is important to get that on the record now, because we might not all be here in future and I hope that future Members will hold that accounting officer personally to account for how the money is spent in this place—and not just here on the Floor of the House when we are discussing estimates but in other forums as well.

The Sponsor Body will set up the Delivery Authority. The people on the Sponsor Body, which has been set up in shadow form, are key figures at the moment. They were appointed for a three-year term and they are less than one year into their term. I echo the comments made by the right hon. Member for Derbyshire Dales (Sir Patrick McLoughlin) about the need for continuity. I am absolutely in favour of open recruitment, but given that these people went through a full and open recruitment process for the very same job—albeit that it is in shadow form rather than in statute and were appointed less than a year ago—there is scope to roll their term over to at least the end of their three-year term and then have the recruitment process continue as normal. I hope the Leader of the House will consider that so we can get started now on this project.

As the hon. Member for Airdrie and Shotts (Neil Gray) said, we discussed in Committee the Government having a Treasury Minister on the Sponsor Body to get Government buy-in. I know there can be issues either way, but we must consider that in Committee to see what skin the Government of the day need to have in the game. Of course, the risk is that the Government of the day could decide to pull the plug; one Treasury Minister would not be able to stop it, but would be able to keep a beady eye on taxpayers’ money, alongside other Members of the House on the Committee.

We talked too about the election of Members to the board, which I naturally support, with one caveat.

Nick Smith Portrait Nick Smith (Blaenau Gwent) (Lab)
- Hansard - -

My hon. Friend is making some very thoughtful remarks. Has she given thought to how parliamentary questions can be laid and a Minister respond to scrutiny from the Chamber?

Meg Hillier Portrait Meg Hillier
- Hansard - - - Excerpts

The Joint Committee gave some thought to this, and the view was that members of the Sponsor Body should come to the House as Members representing the House of Commons Commission and others representing the Church Commissioners do to answer from the Back Benches. We learned from the hon. Member for Caithness, Sutherland and Easter Ross (Jamie Stone) that the more open we are the better, so I would say that that infrequent appearance might not be enough, and at certain points in the project we might want to have far more open access both to Members of this House and the media, because it is not just Members of this House who need to know about it; this is a taxpayer-funded project that the people of the UK need to know about and they need to know that questions can be asked about it.

We need to make sure we scrutinise this fully and properly. I talked about the election of members to the Sponsor Body. We on the Committee wanted that, but the Government did not accept it. My one caveat about having elections is that we must make sure we have full balance across the House. I will probably want to press this in Committee, because we want to make sure that, for example, smaller parties such as the SNP are not disadvantaged if there is an open vote across the House and Members vote on party lines, as may happen. Given the excellent support and input of the hon. Member for Airdrie and Shotts and others, it would be invidious to cut out a Member because their party label meant they would not secure the votes. That must be considered, but of course in principle I support elections for all the reasons that others have highlighted.

The scrutiny of this project is vital. This House will scrutinise it, the Estimates Commission will put the proposals forward and, thanks to the mechanism worked up with the Procedure Committee through the Backbench Business Committee, we can get those estimates and discuss them and the detail here.

We have made sure that under the Bill the National Audit Office will have the powers to audit the Sponsor Body, the Delivery Authority and the project. The Public Accounts Committee will, as of right, be able to hold evidence sessions on the National Audit Office reports and examine the numbers in detail. I will no longer be the Chair of the Public Accounts Committee when all this happens, although I hope to have some input in the early stages. I am laying down a marker for my successors, however, because the length of the project means that at least another couple of Select Committee Chairs will be looking at this.

--- Later in debate ---
Kevin Foster Portrait Kevin Foster
- Hansard - - - Excerpts

I thank the hon. Gentleman for his intervention. Of course I take an interest in the remarks that have been made. These works have been looked at on many occasions by professional advisers who are coming up with appropriate things. We can all talk about being imaginative, but the reality is that there has been a great deal of analysis that has gone into this project. Come 2021, the House will again be able to scrutinise the detail of business cases, to take votes based on real estimates and to scrutinise the estimates to ensure that everyone has the information that they need to make a decision.

Nick Smith Portrait Nick Smith
- Hansard - -

On this topic of possible cost overruns, a number of colleagues have talked about the possibility of the northern estate being delayed because of planning problems, which could be very expensive indeed. Can the Minister tell us more about that possibility and how we are going to reduce that risk?

Kevin Foster Portrait Kevin Foster
- Hansard - - - Excerpts

I thank the hon. Gentleman for his intervention. On planning, he will be aware that this project will follow the usual planning rules. We do not intend to make Parliament a special case; we will still liaise with Westminster City Council. On the detail in relation to the northern estate, I am happy to write to him and also place a copy of that letter in the Library. That would enable me to give him a detailed reply to his concerns. I am conscious though that, when we engage with the city council, we will do so as any other applicant would. We must be very clear that we are not setting ourselves in a special place because we are the UK Parliament.

Let me move on now to the comments of my right hon. Friend the Member for Derbyshire Dales (Sir Patrick McLoughlin). He quite rightly pointed out that, if this building were in private hands, we would insist on its repair via the law that we pass. That also applies in terms of conserving its heritage. I also pay tribute to the role that he plays on the shadow Sponsor Body, bringing his considerable experience of Parliament to bear in doing so.

It is always a pleasure to hear from the hon. Member for Rhondda (Chris Bryant). I know that, like me, he also managed to nip into the other debate to make a contribution, showing his passion for his work. Again, mention was made of his work on the Joint Committee of 2016. It was almost as if we managed to duplicate ourselves to ensure that we could achieve the feat of being in two places at once. We appreciate the comments that were made, especially the ones around planning, but again I have to say that there is a difference between these works and the works of the Olympics in terms of not having four different projects and of not having four different planning authorities. Again I say, it would be a low step for Parliament to look to put itself above other procedures and other organisations dealing with similar buildings.

My hon. Friend the Member for Mole Valley (Sir Paul Beresford) talked about the iconic nature of this building and the vast scale of the task—no one can underestimate the vast scale of the task. On the nature of this building, I sometimes make the point on a tour that this is probably one of the few places that literally has history attached to a broom cupboard because of what happened on the night of the 1911 census. Again, it rams home the fact that every part of this building has a history.

Let me move on to the comments of the hon. Member for Airdrie and Shotts (Neil Gray) who gave us his considered thoughts. I note that he said that he wanted a Treasury Minister on the Sponsor Body. The point that I make is that we are clear that this is a parliamentary project, not a Government project. I also noted the comments of the hon. Member for Hackney South and Shoreditch (Meg Hillier), who said that we can explore that matter in the Bill Committee. The Government’s view is that, while there will be some engagement with the Treasury, a Minister being on the board could confuse the roles and may not necessarily be the best way of ensuring that this project progresses.

My right hon. Friend the Member for Gainsborough (Sir Edward Leigh), as always, gave a passionate speech showing his great knowledge and skill, and making very clear the risks that we are running if we decide not to grasp this nettle. He talked us through the options. I know he has been a passionate proponent of particular outcomes for this project, but it is right that whatever option we look to take—whatever our thoughts on particular aspects of the project—we move on with this Bill and set up the Delivery Authority to allow it to happen.

It was interesting to hear the experience of the hon. Member for Caithness, Sutherland and Easter Ross (Jamie Stone) with the Scottish Parliament building. I actually saw the desk to which he referred only last week when I visited my opposite number in the Scottish Government. The hon. Gentleman is probably right to say that there will be some flak along the way in this project; that is almost inevitable. However, he is also right to say that this needs to be a project across the whole Union, not just one for the normal contractors, and that it should be something in which we can all take pride.

I found the comments of the hon. Member for Hackney South and Shoreditch particularly interesting, as she outlined the role that the Public Accounts Committee will look to play in overseeing this work. As she reflected, it was the work of the hon. Lady and her Committee that persuaded many Members to vote for the motion, given that the House supported her amendment by a majority and then supported the substantive motion that has brought us to where we are today. I am sure that many Members of the House will hope that such an approach will continue.

It is extremely important that we make progress with the restoration and renewal project so that we can secure this historic Palace for future generations. That is why I am pleased that the House passed the motions in 2018 voting for a full decant, and why I am pleased that this Bill is being debated today. As the Joint Committee on the Palace of Westminster said in its report, the Sponsor Body will need to set clear timelines for completing the vital works. It is very much my hope that we move back into this historic and iconic building as swiftly as possible afterwards. Indeed, the Bill provides for this. At the point that we vote on the design and funding for the project, we will have a better understanding of the timescales and will be proceeding—if it is the decision of the House—based on that timetable. If the timetable or costs shift significantly, the House will have the opportunity to vote again.

Concerns have rightly been raised about the cost of this project, and we are determined to ensure that the R and R programme represents best value for money for the taxpayer. That will be the guiding principle as we take this Bill forward. We are confident that the governance arrangements set out in the Bill can and will deliver the necessary restoration works while guaranteeing value for money for the taxpayer, as there is not an unlimited amount of available funds.

The Bill puts in place a number of core financial safeguards that have been signed off by the Chief Secretary to the Treasury. To mention just a few: Parliament will be given an opportunity to vote on the annual expenditure of the Sponsor Body; the Estimates Commission will have the power to reject draft estimates if the project is going over budget; the Comptroller and Auditor General will conduct annual financial audits in relation to both the Sponsor Body and the Delivery Authority, and of course has the relationship with the Public Accounts Committee that the Committee’s Chair touched on in her speech; and finally, Parliament will vote on the cost of the substantive building works. The Government are clear that the work must represent good value for tax- payers’ money, and the programme needs to be delivered on time and on budget.

The R and R programme is at its heart, and will continue to be, a parliamentary project. That is why the Bill ensures that parliamentarians have a clear voice as members of the Sponsor Body, and establishes a specific duty on the Sponsor Body to consult with parliamentarians on strategic objectives for the restoration and renewal works. Parliament will also have a significant role in approving the proposals for the works, including the scope, delivery method and cost.

The importance of engaging the public has also been mentioned, and I completely agree that the public need to have a clear voice in this historic project about the Parliament that represents them. This project will provide an unparalleled opportunity to get the public to engage with Parliament and democracy—both during the programme and through providing a lasting legacy. How we engage the public in R and R is ultimately for the Sponsor Body to define, working alongside the Delivery Authority. However, the Sponsor Body will have the chance to engage innovatively with the wider public about restoration and renewal, and I would expect that to be across the entire United Kingdom, as I touched on earlier.

If I may sum up, this Bill ensures that we establish the governance bodies that will be able—