Asked by: Tim Farron (Liberal Democrat - Westmorland and Lonsdale)
Question to the Department for Transport:
To ask the Secretary of State for Transport, when any assessment by National Highways of temporary slip roads at Junction 38 of the M6 was undertaken; and whether the findings of that assessment informed the current construction programme.
Answered by Simon Lightwood - Parliamentary Under-Secretary (Department for Transport)
National Highways first assessed the potential for temporary slip roads during the project’s optioneering stage in 2019. Further consideration took place during early design development, and the option was not taken forward at that time due to spatial constraints, value for money considerations, the need for significant lane and speed restrictions, and the likelihood of a costly extension to the overall construction period.
In 2025, following engagement with local stakeholders, National Highways committed to revisit this option, with a feasibility exercise carried out in August 2025. This re-considered the option of temporary slip roads. The exercise supported the conclusions during the early design phase; specifically, that temporary slip roads were unsuitable due to the space needed to construct the bridge decks, as well as representing poor value for money. During 2025, the programme has also assessed a wide range of options to improve connectivity, and this resulted in the decision to defer work on Lawtland House bridge to a future date, improving local connectivity during the construction period.
When National Highways presented their findings from the feasibility exercise, a revised construction methodology was submitted by BWB Consulting on behalf of local stakeholders in October 2025. National Highways has committed to review this proposal from BWB consulting to see if it has presented an alternative viable solution. The review will conclude in January 2026.
Asked by: Tim Farron (Liberal Democrat - Westmorland and Lonsdale)
Question to the Department for Transport:
To ask the Secretary of State for Transport, whether National Highways undertook a detailed assessment of the potential to construct temporary slip roads to allow Junction 38 of the M6 (northbound and southbound) to remain open for the duration of the Lune Gorge bridge replacement works; and whether that assessment was completed before the current construction programme was designed and approved.
Answered by Simon Lightwood - Parliamentary Under-Secretary (Department for Transport)
National Highways first assessed the potential for temporary slip roads during the project’s optioneering stage in 2019. Further consideration took place during early design development, and the option was not taken forward at that time due to spatial constraints, value for money considerations, the need for significant lane and speed restrictions, and the likelihood of a costly extension to the overall construction period. The construction programme and design was then taken forward on that basis.
In 2025, following engagement with local stakeholders, National Highways committed to revisit this option, with a feasibility exercise carried out in August 2025. This re-considered the option of temporary slip roads. The exercise supported the conclusions during the early design phase; specifically, that temporary slip roads were unsuitable due to the space needed to construct the bridge decks, as well as representing poor value for money. During 2025, the programme assessed a wide range of options to improve connectivity, and resulted in the decision to defer work on Lawtland House bridge to a future date, improving local connectivity during the construction period.
When National Highways presented their findings from the feasibility exercise, a revised construction methodology was submitted by BWB Consulting on behalf of local stakeholders in October 2025. National Highways has committed to review this proposal from BWB consulting to see if it has presented an alternative viable solution. The review will conclude in January 2026.
Asked by: Tim Farron (Liberal Democrat - Westmorland and Lonsdale)
Question to the Department for Transport:
To ask the Secretary of State for Transport, what assessment she has made of the potential impact of closing Junction 38 of the M6 during the Lune Gorge bridge replacement works on local businesses.
Answered by Simon Lightwood - Parliamentary Under-Secretary (Department for Transport)
This Government, working in close partnership with National Highways, is fully committed to this project being delivered in a way that minimises disruption to road users, businesses and local communities. National Highways has undertaken assessments to understand the impact this work will have on the region including an assessment of the impact on traffic flows of the proposed traffic management arrangements. National Highways is also reviewing a detailed feasibility report of proposals for Junction 38 which was provided last year. The review is expected to conclude in January 2026.
Asked by: Tim Farron (Liberal Democrat - Westmorland and Lonsdale)
Question to the Department for Transport:
To ask the Secretary of State for Transport, whether he will instruct National Highways to meet with BWB Consulting and Kier in an engineer-to-engineer review of proposals for temporary slip roads at Junction 38 of the M6.
Answered by Simon Lightwood - Parliamentary Under-Secretary (Department for Transport)
National Highways has facilitated discussions between BWB Consulting and Kier engineers, including a meeting held on 17 December 2025 to review proposals for temporary slip roads at Junction 38. A further update on temporary slip roads will be provided at the Stakeholder Engagement Group meeting at the end of January 2026.
Asked by: Tim Farron (Liberal Democrat - Westmorland and Lonsdale)
Question to the Department for Transport:
To ask the Secretary of State for Transport, when she plans to seek new nominations for another round of mid-tier Access for All funding.
Answered by Simon Lightwood - Parliamentary Under-Secretary (Department for Transport)
Spending Review 2025 confirmed £280m total funding for the Access for All programme over a four-year period. Our focus is on delivering full step free access at stations, rather than the smaller scale upgrades previously delivered under the mid-tier. As such, we have no current plans to fund a future round of mid-tier projects.