Heathrow Substation Outage: NESO Review Debate

Full Debate: Read Full Debate
Department: Department for Energy Security & Net Zero

Heathrow Substation Outage: NESO Review

Tom Collins Excerpts
Wednesday 2nd July 2025

(2 days ago)

Commons Chamber
Read Full debate Read Hansard Text Watch Debate Read Debate Ministerial Extracts
Michael Shanks Portrait Michael Shanks
- View Speech - Hansard - - - Excerpts

The hon. Gentleman may be confusing two things. The National Energy System Operator is no longer part of National Grid, as it was made into a publicly owned company by the previous Government, which was introduced by us when we came into Government. So the National Energy System Operator is responsible for managing the energy system and it is different from National Grid, which is a private company that operates the electricity network in England, so those two organisations are slightly different. Of course, he is right to highlight the scale of the failure. That is why I have given a statement today and why a number of serious actions are being taken, which will be followed up in a serious way.

We did not come close to a blackout earlier this year. It is important to repeat that, because there is a lot of misinformation about a particular set of statistics that were misunderstood by some people. We have never come close to that and we have never had a national power outage in our history. The aim of all the work that we do is to build as safe and resilient an electricity system as we can, so that when circumstances like this happen—because fires and accidents do happen—we will have done everything that we could have done to have mitigations in place. When such a fault is down to a failure of maintenance, we must ensure that is taken account of and never happens again.

Tom Collins Portrait Tom Collins (Worcester) (Lab)
- View Speech - Hansard - -

Like any serious incident, this one had multiple causes, both operational and relating to design. I urge the Minister to ensure that the lessons learned are applied not only to electricity transmission and distribution sites, but to energy storage sites, for which we have an absence of standards. He rightly mentioned the need for redundancy and flexibility in our electricity systems, and the need to avoid having single points of failure. That applies well to large pieces of essential infrastructure, but is harder with our distributed critical infrastructure, for example around telecommunications, so we need diversity in our energy system as a whole. Does he agree that in our energy system, we need widespread availability from multiple parts of the energy sector, with electricity being backed up by, for example, hydrogen and ammonia?

Michael Shanks Portrait Michael Shanks
- View Speech - Hansard - - - Excerpts

My hon. Friend always reminds me how much he knows about many of these issues; it is hugely welcome. He is right: there are wider lessons to be learned across the system, and not just for large critical national infrastructure. As he says, we have a grid that has many more power stations, of different forms, than we have ever had in the past. There are also lessons to be learned for storage, which is rightly becoming increasingly important for our energy mix.

On his wider point about telecoms, in the wake of the storms earlier this year, we took a number of actions to make our electricity system more resilient. Our use of telecommunications equipment in this country is changing. Very few people now have access to traditional copper wire phones, so when telecoms equipment goes down, there is an immediate significant impact on people’s lives. I recently met the Minister for Data Protection and Telecoms in the Department for Science, Innovation and Technology to discuss this issue. We will work with Ofcom and the operators to ensure that the telecoms infrastructure is as resilient as it can be.