Chemicals: Regulation

(asked on 2nd January 2026) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask the Secretary of State for Environment, Food and Rural Affairs, whether the average length of time required for chemical (a) production and (b) processing sites to be permitted by the Environment Agency varies by region.


Answered by
Emma Hardy Portrait
Emma Hardy
Parliamentary Under-Secretary (Department for Environment, Food and Rural Affairs)
This question was answered on 7th January 2026

The Environment Agency’s (EA) target assessment time to process chemical production or processing permit applications is 250 days. These permits are among the most complex the EA handles, involving thorough assessments to protect the environment and public, and to ensure operators are supported and can comply with necessary permit conditions. Over the last 12 months the EA has issued within an average of 260 days.