National Energy System Operator: Members

(asked on 2nd January 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, if he will impose a duty on the National Energy System Operator to inform hon. Members of connection applications in their constituencies.


Answered by
Michael Shanks Portrait
Michael Shanks
Minister of State (Department for Energy Security and Net Zero)
This question was answered on 12th January 2026

Network connection applications are confidential to the parties involved before the point of a contract being signed, but details of generation and storage transmission connection agreements are published in the Transmission Entry Capacity Register TEC Register | National Energy System Operator. The equivalent for Interconnector projects is at Interconnector Register | National Energy System Operator.